7714 N LASAINE AVE 91325

Certificate Information: 7714 N LASAINE AVE 91325

Application / Permit
24014-20000-03268
Plan Check / Job No.
B24VN10723
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 37' X 5'-2" TO THE FRONT OF EXISTING SINGLE FAMILY DWELLING; ADD 23'-11" X 17' IRREGULAR SHAPE TO THE REAR OF SFD; ADD 3' X 8'-6" PORCH TO THE FRONT OF SFD; INTERIOR REMODEL; REFRAME ROOF
Permit Issued
Issued on 8/6/2024
Issuing Office
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 SELLA BENYAMIN
Corrections Issued 7/30/2024 SELLA BENYAMIN
Building Plans Picked Up 8/2/2024 APPLICANT
Quality Review Completed 8/6/2024 SELLA BENYAMIN
Plan Check Approved 8/6/2024 SELLA BENYAMIN
Issued 8/6/2024 APPLICANT
CofO in Progress 11/27/2024 SALVADOR MARTINEZ
Permit Finaled 12/3/2024 DANIEL ORRANTE
CofO Issued 12/3/2024 DANIEL ORRANTE
Permit Finaled 12/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/30/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/30/2024 LEE GUILBEAUX
Sewer availability Cleared 7/30/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/30/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 8/12/2024 Partial Approval RAUL OLAGI
Sewer 8/12/2024 Approved RAUL OLAGI
Deputy Drilled-In Anchors 8/13/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/16/2024 Approved RAUL OLAGI
Special/Order Compliance 8/16/2024 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 8/19/2024 Approved RAUL OLAGI
Pre-Inspection 8/19/2024 Approved RAUL OLAGI
Deputy Drilled-In Anchors 8/28/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/28/2024 Approved RAUL OLAGI
PLUMBING-Rough 9/9/2024 Approved RAUL OLAGI
Deputy Drilled-In Anchors 9/16/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 9/16/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 9/20/2024 Approved RAUL OLAGI
HVAC-Rough 9/20/2024 Approved RAUL OLAGI
Shower Pan 9/20/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 10/3/2024 Approved RAUL OLAGI
Green Building Rough 10/3/2024 Approved RAUL OLAGI
Insulation 10/3/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 10/3/2024 Approved RAUL OLAGI
Drywall Nailing 10/7/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Drywall Nailing 10/8/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 10/8/2024 Approved MICHAEL CORTEZ
Final 11/13/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/13/2024 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 11/13/2024 Approved SALVADOR MARTINEZ
Final 11/18/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/18/2024 Approved SALVADOR MARTINEZ
Final 11/21/2024 OK to Issue CofO SALVADOR MARTINEZ