10653 N LANGMUIR AVE 91040

Certificate Information: 10653 N LANGMUIR AVE 91040

Application / Permit
24014-20000-03259
Plan Check / Job No.
B24VN10676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT W/ (N) 8'-10" x 18'-8" ADDITION (149 SF) PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/3/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 SEAN SHAHMIRI
Corrections Issued 8/15/2024 SEAN SHAHMIRI
Quality Review Completed 8/15/2024 STEVEN KIM
Building Plans Picked Up 8/15/2024 APPLICANT
Applicant returned to address corrections 12/6/2024 SEAN SHAHMIRI
Plan Check Approved 12/19/2024 SEAN SHAHMIRI
Issued 1/3/2025 APPLICANT
CofO in Progress 9/25/2025 WILLIAM WREN
CofO Issued 10/2/2025 RUBEN SALAS
Permit Finaled 10/2/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/9/2024 BIAINA HARITUNIAN
Address approval Cleared 10/16/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/23/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/29/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 12/6/2024 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 2/18/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 2/18/2025 Partial Approval DAVID ANDERSON
Sewer 2/18/2025 Approved DAVID ANDERSON
Footing/Foundation/Slab 2/21/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 4/1/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 4/1/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved WILLIAM WREN
Green Building Rough 4/1/2025 Approved WILLIAM WREN
HVAC-Rough 4/1/2025 Approved WILLIAM WREN
PLUMBING-Rough 4/1/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 4/16/2025 Partial Approval WILLIAM WREN
Insulation 4/21/2025 Approved WILLIAM WREN
Drywall Nailing 4/28/2025 Approved WILLIAM WREN
Shower Pan 4/28/2025 Corrections Issued WILLIAM WREN
Shower Pan 4/30/2025 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 7/28/2025 Not Ready for Inspection MATTHEW NELSON
Final 7/28/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Final 7/28/2025 Approved MATTHEW NELSON
HVAC-Final 7/28/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 7/28/2025 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 7/28/2025 Not Ready for Inspection MATTHEW NELSON
Final 8/29/2025 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Not Required WILLIAM WREN
Smoke Detectors 8/29/2025 Approved WILLIAM WREN
Final 9/8/2025 OK to Issue CofO WILLIAM WREN