8408 W FENWICK ST 91040

Certificate Information: 8408 W FENWICK ST 91040

Application / Permit
24014-20000-03244
Plan Check / Job No.
B24VN10564
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 13'-5' X 16'-11" ADDITION TO THE (E) SINGLE FAMILY DWELLING ALL WORK PER WFPP
Permit Issued
Issued on 7/31/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/23/2024 PINANK PATEL
Corrections Issued 7/23/2024 PINANK PATEL
Plan Check Approved 7/31/2024 SEWADA ZADOORAN MILAGARDI
Issued 7/31/2024 APPLICANT
CofO in Progress 2/24/2025 WILLIAM WREN
Permit Finaled 3/4/2025 RUBEN SALAS
CofO Issued 3/4/2025 RUBEN SALAS
Permit Finaled 3/4/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/24/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 7/25/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/25/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/9/2024 Partial Approval WILLIAM WREN
Deputy Drilled-In Anchors 12/4/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/4/2024 Approved WILLIAM WREN
PLUMBING-Rough 12/4/2024 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/31/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/31/2024 Partial Inspection CHRISTOPHER ROJAS
HVAC-Rough 12/31/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 12/31/2024 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/3/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 1/3/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Approved WILLIAM WREN
Insulation 1/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 1/9/2025 Partial Approval MATTHEW NELSON
Drywall Nailing 1/14/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 1/14/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 1/30/2025 Approved WILLIAM WREN
Final 1/30/2025 Corrections Issued WILLIAM WREN
Green Building Final 1/30/2025 Not Ready for Inspection WILLIAM WREN
Green Building Rough 1/30/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 1/30/2025 Approved WILLIAM WREN
Final 2/4/2025 OK to Issue CofO WILLIAM WREN
Green Building Final 2/4/2025 Approved WILLIAM WREN