15404 W LEADWELL ST 91406

Certificate Information: 15404 W LEADWELL ST 91406

Application / Permit
24014-20000-03210
Plan Check / Job No.
B24VN10376
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INT/EXT REMODEL - CONVERT EX ATTACHED GARAGE INTO BEDRM/BATHRM/CLOSET. ENCLOSE EX BREEZEWAY FOR A NEW CLOSET. NEW FRONT PORCH, LAUNDRY RM & HALLWAY ADDN. NEW 40'X12' PATIO COVER ADDN AT REAR. CONVERT EX LAUNDRY & 1/2 BATH INTO PANTRY. REMODEL EX KITCHEN, BATHRM & BEDRM PER PLAN. REMOVE & REPLACE ALL EXTERIOR WINDOWS & DOORS PER PLAN.
Permit Issued
Issued on 9/27/2024
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2024 APPLICANT
Assigned to Plan Check Engineer 7/29/2024 JESSE ARELLANO
Corrections Issued 7/31/2024 JESSE ARELLANO
Building Plans Picked Up 8/1/2024 APPLICANT
Applicant returned to address corrections 9/20/2024 ISIS ARGUETA
Applicant returned to address corrections 9/23/2024 HAYATO TSUCHIYA
Applicant returned to address corrections 9/26/2024 KAMYAR EMAMI
Plan Check Approved 9/27/2024 SARKIS HARABEDIAN
Issued 9/27/2024 APPLICANT
CofO in Progress 1/30/2026 VINCENT HANLEY
Permit Finaled 2/20/2026 RUBEN SALAS
CofO Issued 2/20/2026 RUBEN SALAS
Permit Finaled 2/20/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/5/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/16/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/29/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 10/29/2024 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 11/4/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 11/14/2024 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 2/18/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 3/21/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/21/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Approved VINCENT HANLEY
Green Building Rough 3/21/2025 Approved VINCENT HANLEY
HVAC-Rough 3/21/2025 Approved VINCENT HANLEY
PLUMBING-Rough 3/21/2025 Approved VINCENT HANLEY
Insulation 3/25/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/25/2025 Partial Approval VINCENT HANLEY
Drywall Nailing 4/2/2025 Approved MISAEL ESPARZA
Shower Pan 4/2/2025 Partial Approval MISAEL ESPARZA
Shower Pan 4/8/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/18/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 1/29/2026 Approved VINCENT HANLEY
Final 1/29/2026 OK to Issue CofO VINCENT HANLEY
Green Building Final 1/29/2026 Approved VINCENT HANLEY
HVAC-Final 1/29/2026 Approved VINCENT HANLEY
PLUMBING-Final 1/29/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/29/2026 Approved VINCENT HANLEY