4098 N ALCOVE AVE 91604
Certificate Information: 4098 N ALCOVE AVE 91604
- Application / Permit
- 24014-20000-03203
- Plan Check / Job No.
- B24VN10344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH ADDITIONS. CONSTRUCTION PER ENGR DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 05/03/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Current Status
- CofO Issued on 7/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 7/30/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 8/13/2024 | APPLICANT |
| Plan Check Approved | 1/14/2025 | HAYATO TSUCHIYA |
| Issued | 1/14/2025 | APPLICANT |
| CofO in Progress | 7/8/2025 | PTOLEMY HILL |
| Permit Finaled | 7/28/2025 | DANIEL SANCHEZ |
| CofO Issued | 7/28/2025 | DANIEL SANCHEZ |
| Permit Finaled | 7/28/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/23/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/25/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 9/25/2024 | RUBEN VASQUEZ |
| Construction within easement | Cleared | 11/19/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/16/2024 | JERRY KAO |
| Grading Pre-Inspection | Cleared | 12/17/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/16/2025 | Approved | PTOLEMY HILL |
| Deputy Drilled-In Anchors | 1/21/2025 | Conditional Approval | PTOLEMY HILL |
| Excavation/Setback/Form/Re-Bar | 1/22/2025 | Approved | PTOLEMY HILL |
| Footing/Foundation/Slab | 1/22/2025 | Approved | PTOLEMY HILL |
| Underground Mechanical | 1/22/2025 | Approved | PTOLEMY HILL |
| Deputy Reinf. Concrete | 1/24/2025 | Conditional Approval | PTOLEMY HILL |
| BUILDING-Rough-Frame | 2/14/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| ELECTRICAL-Rough | 2/14/2025 | Approved | JONATHAN FRANCHINI |
| Gas Test | 2/14/2025 | Approved | JONATHAN FRANCHINI |
| Green Building Rough | 2/14/2025 | Not Ready for Inspection | JONATHAN FRANCHINI |
| PLUMBING-Rough | 2/14/2025 | Approved | JONATHAN FRANCHINI |
| Deputy Wood Construction | 2/18/2025 | Partial Approval | JOEL ORDAZ |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | JONATHAN FRANCHINI |
| HVAC-Rough | 2/20/2025 | Partial Approval | JONATHAN FRANCHINI |
| Insulation | 2/20/2025 | Approved | JONATHAN FRANCHINI |
| Drywall Nailing | 2/24/2025 | Approved | PTOLEMY HILL |
| Green Building Rough | 2/24/2025 | Approved | PTOLEMY HILL |
| Interior/Exterior Lathing | 3/18/2025 | Corrections Issued | PTOLEMY HILL |
| Interior/Exterior Lathing | 3/20/2025 | Approved | PTOLEMY HILL |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | PTOLEMY HILL |
| ELECTRICAL-Final | 4/17/2025 | Corrections Issued | PTOLEMY HILL |
| Final | 4/17/2025 | Corrections Issued | PTOLEMY HILL |
| Green Building Final | 4/17/2025 | Not Ready for Inspection | PTOLEMY HILL |
| HVAC-Final | 4/17/2025 | Corrections Issued | PTOLEMY HILL |
| PLUMBING-Final | 4/17/2025 | Approved | PTOLEMY HILL |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | PTOLEMY HILL |
| Smoke Detectors | 4/17/2025 | Approved | PTOLEMY HILL |
| Final | 4/21/2025 | OK to Issue CofO | PTOLEMY HILL |
| Green Building Final | 4/21/2025 | Approved | PTOLEMY HILL |