5750 N BECK AVE 91601

Certificate Information: 5750 N BECK AVE 91601

Application / Permit
24014-20000-03191
Plan Check / Job No.
B24VN10284
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. Addition to existing garage creating and an ADU and garage per ordinance. All work done per engineering.
Permit Issued
Issued on 11/19/2024
Issuing Office
Current Status
CofO Issued on 6/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2024 APPLICANT
Assigned to Plan Check Engineer 7/24/2024 DANIEL SMILEY
Corrections Issued 7/25/2024 DANIEL SMILEY
Applicant returned to address corrections 11/13/2024 SUNMIN LEE
Plan Check Approved 11/15/2024 SUNMIN LEE
Issued 11/19/2024 APPLICANT
CofO in Progress 5/16/2025 JAVIER RAMOS JR
Permit Finaled 6/13/2025 RUBEN SALAS
CofO Issued 6/13/2025 RUBEN SALAS
Permit Finaled 6/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/30/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/30/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/31/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/31/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 11/7/2024 RIDWAN HARDY
Construction within easement Cleared 11/7/2024 RIDWAN HARDY

Contact Information

Contractor Dwell Homes Llc; Lic. No.: 1030158-B       ,
Contractor Dwell Homes Los Angeles; Lic. No.: 1030158-B       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/12/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 12/17/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/20/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Corrections Issued JOSE AVILA
HVAC-Rough 1/14/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 1/16/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/16/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/17/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/22/2025 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 1/22/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 1/22/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 1/22/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/28/2025 Partial Approval MICHAEL CORTEZ
Insulation 1/30/2025 Approved CHRISTOPHER ROJAS
Shower Pan 1/30/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 2/3/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 2/3/2025 Approved LOUIS ESCOTO
Sewer 2/26/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/30/2025 Corrections Issued JAVIER RAMOS JR
Final 4/30/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/30/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 4/30/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 4/30/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 4/30/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/16/2025 Approved JAVIER RAMOS JR
Final 5/16/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/16/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 5/16/2025 Approved JAVIER RAMOS JR