10400 1/2 N MEMORY PARK AVE 91345
Certificate Information: 10400 1/2 N MEMORY PARK AVE 91345
- Application / Permit
- 24014-20000-03186
- Plan Check / Job No.
- B24VN10275
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion of existing detached garage to ADU per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2024 | CAROLEAN BASMA |
| Corrections Issued | 7/25/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 11/22/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 11/26/2024 | KAVIAN REFAHI |
| Plan Check Approved | 12/3/2024 | KAVIAN REFAHI |
| Issued | 12/4/2024 | APPLICANT |
| CofO in Progress | 6/6/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 6/10/2025 | RUBEN SALAS |
| CofO Issued | 6/10/2025 | RUBEN SALAS |
| Permit Finaled | 6/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/3/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/5/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
| Engineer | Vartanian,, Albert; Lic. No.: NA39989 | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/10/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 1/28/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 1/31/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/31/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/31/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 2/14/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 2/26/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/28/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/28/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/28/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/4/2025 | Approved | LOUIS ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Corrections Issued | DAVID ANDERSON |
| Drywall Nailing | 3/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 3/12/2025 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 3/12/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 3/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 3/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/14/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/16/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/2/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 5/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/2/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/20/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/20/2025 | Approved | JENNIFER RABUCHIN |