10664 N LOUISE AVE 91344
Certificate Information: 10664 N LOUISE AVE 91344
- Application / Permit
- 24014-20000-03184
- Plan Check / Job No.
- B24VN10272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan - addition and major remodel to (E) 1-story SFD R3 occupancy NFPA 13D sprinklered throughout
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2024 | KELVIN CHUONG |
| Corrections Issued | 7/25/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 8/8/2024 | KELVIN CHUONG |
| Plan Check Approved | 9/5/2024 | KELVIN CHUONG |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 8/11/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/19/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/19/2024 | CARLOS AGUILERA |
| ZI | Cleared | 8/21/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keykhosropour,, Lohrasb; Lic. No.: NA92871 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/18/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 10/18/2024 | Partial Approval | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/29/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/27/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 12/19/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/18/2025 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 2/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/26/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/10/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/10/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/10/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/10/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/10/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 3/10/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 3/19/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 3/24/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 4/21/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/23/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 7/29/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 7/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/29/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 8/4/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 8/4/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 8/4/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 8/4/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/8/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| PLUMBING-Final | 8/8/2025 | Approved | CHRISTOPHER ROJAS |