10664 N LOUISE AVE 91344

Certificate Information: 10664 N LOUISE AVE 91344

Application / Permit
24014-20000-03184
Plan Check / Job No.
B24VN10272
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan - addition and major remodel to (E) 1-story SFD R3 occupancy NFPA 13D sprinklered throughout
Permit Issued
Issued on 9/5/2024
Issuing Office
Current Status
CofO Issued on 8/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2024 APPLICANT
Assigned to Plan Check Engineer 7/24/2024 KELVIN CHUONG
Corrections Issued 7/25/2024 KELVIN CHUONG
Applicant returned to address corrections 8/8/2024 KELVIN CHUONG
Plan Check Approved 9/5/2024 KELVIN CHUONG
Issued 9/5/2024 APPLICANT
CofO in Progress 8/11/2025 CHRISTOPHER ROJAS
Permit Finaled 8/14/2025 RUBEN SALAS
CofO Issued 8/14/2025 RUBEN SALAS
Permit Finaled 8/14/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/19/2024 CARLOS AGUILERA
Sewer availability Cleared 8/19/2024 CARLOS AGUILERA
ZI Cleared 8/21/2024 ALEX VELA

Contact Information

Contractor Owner-Builder       ,
Engineer Keykhosropour,, Lohrasb; Lic. No.: NA92871       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/18/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 10/18/2024 Partial Approval KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 10/29/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/29/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/27/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Approved JAVIER RAMOS JR
Wood Frame 12/19/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/18/2025 Partial Approval JAVIER RAMOS JR
HVAC-Rough 2/18/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/18/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 2/26/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/10/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 3/10/2025 Approved JAVIER RAMOS JR
Green Building Rough 3/10/2025 Approved JAVIER RAMOS JR
HVAC-Rough 3/10/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/10/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 3/10/2025 Approved JAVIER RAMOS JR
Insulation 3/19/2025 Approved LOUIS ESCOTO
Drywall Nailing 3/24/2025 Approved CHRISTOPHER ROJAS
Shower Pan 4/21/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/23/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 7/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 7/29/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 7/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 7/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 7/29/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 8/4/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/4/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 8/4/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 8/4/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 8/4/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/8/2025 OK to Issue CofO CHRISTOPHER ROJAS
PLUMBING-Final 8/8/2025 Approved CHRISTOPHER ROJAS