10427 W SEABURY LANE 90077

Certificate Information: 10427 W SEABURY LANE 90077

Application / Permit
24014-20000-03150
Plan Check / Job No.
B24VN10165
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION ABOVE THE (E) DETACHED GARAGE TO BE A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER DESIGN
Permit Issued
Issued on 9/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 ALFRED RAMIREZ
Corrections Issued 8/12/2024 ALFRED RAMIREZ
Quality Review Completed 8/15/2024 STEVEN KIM
Building Plans Picked Up 8/30/2024 APPLICANT
Applicant returned to address corrections 9/6/2024 ALFRED RAMIREZ
Plan Check Approved 9/10/2024 ALFRED RAMIREZ
Issued 9/10/2024 APPLICANT
CofO in Progress 8/14/2025 SEAN HAUPT
Permit Finaled 8/26/2025 RICHARD STEINBACH
CofO Issued 8/26/2025 RICHARD STEINBACH
Permit Finaled 8/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/31/2024 DARIN LAM
BHO/Hillside ordinance Cleared 8/31/2024 DARIN LAM
Roof/Waste drainage to street Cleared 8/31/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/5/2024 DARIN LAM
Sewer availability Cleared 9/5/2024 DARIN LAM

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 1816 HILLCREST AVENUE      GLENDALE, CA 91202
Contractor Owner-Builder       ,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/29/2025 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 2/3/2025 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 2/20/2025 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Approved SEAN HAUPT
HVAC-Rough 2/20/2025 Approved SEAN HAUPT
PLUMBING-Rough 2/20/2025 Approved SEAN HAUPT
Special/Order Compliance 2/20/2025 Approved SEAN HAUPT
Underground Mechanical 2/20/2025 Partial Approval SEAN HAUPT
Insulation 2/27/2025 Corrections Issued SEAN HAUPT
Interior/Exterior Lathing 2/27/2025 Partial Approval SEAN HAUPT
Shower Pan 2/27/2025 Approved SEAN HAUPT
Special/Order Compliance 2/27/2025 Partial Inspection BOBBY KEY
Insulation 3/5/2025 Partial Approval REGINA MENDEZ
Interior/Exterior Lathing 3/5/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 3/19/2025 Approved SEAN HAUPT
Green Building Rough 3/19/2025 Approved SEAN HAUPT
Insulation 3/19/2025 Approved SEAN HAUPT
Underground Mechanical 3/19/2025 Approved SEAN HAUPT
Verify Sprinkler Sign Off 3/19/2025 Approved SEAN HAUPT
Drywall Nailing 3/21/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 6/20/2025 Approved STEPHANIE SWANSON
Final 6/20/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 6/20/2025 Approved STEPHANIE SWANSON
Green Building Final 6/20/2025 Approved STEPHANIE SWANSON
HVAC-Final 6/20/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 6/20/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Not Required STEPHANIE SWANSON
Smoke Detectors 6/20/2025 Corrections Issued STEPHANIE SWANSON
Final 8/14/2025 OK to Issue CofO SEAN HAUPT
Smoke Detectors 8/14/2025 Approved SEAN HAUPT
Special/Order Compliance 8/14/2025 Approved SEAN HAUPT