7221 S OGELSBY AVE 90045

Certificate Information: 7221 S OGELSBY AVE 90045

Application / Permit
24014-20000-03144
Plan Check / Job No.
B24VN10152
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (15'-0"x10'-0"), 150 SQFT ADDITION OF A SUNROOM/PATIO COVER PER ENGINEER DESIGN.
Permit Issued
Issued on 10/4/2024
Issuing Office
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 PETER MOSESIAN
Corrections Issued 7/27/2024 PETER MOSESIAN
Quality Review Completed 7/31/2024 OMID HEDAYAT
Building Plans Picked Up 8/1/2024 APPLICANT
Plan Check Approved 10/4/2024 PETER MOSESIAN
Issued 10/4/2024 APPLICANT
CofO in Progress 12/18/2024 MICHAEL ALLEN
Permit Finaled 12/31/2024 RICHARD STEINBACH
CofO Issued 12/31/2024 RICHARD STEINBACH
Permit Finaled 12/31/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/5/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 8/5/2024 HISASHI KOBAYAKAWA
Specific Plan Cleared 10/2/2024 HAMID GHAEMMAGHAMI

Contact Information

Contractor Right Choice Home Remodeling Inc The; Lic. No.: 1066456-B 15315 MAGNOLIA BLVD #429      SHERMAN OAKS, CA 91403
Engineer Hofmann,, Jeffrey Erwin; Lic. No.: C47407 9198 GREENBACK LN #116      ORANGEVALE, CA 95662

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/5/2024 Not Ready for Inspection MICHAEL ALLEN
BUILDING-Rough-Frame 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
Drywall Nailing 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
Final 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
Footing/Foundation/Slab 11/7/2024 Corrections Issued MICHAEL ALLEN
METHANE-Barrier 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
METHANE-Final 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
METHANE-Subgrade 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
Smoke Detectors 11/7/2024 Not Ready for Inspection MICHAEL ALLEN
Special/Order Compliance 11/7/2024 Partial Inspection HERBERT GIRON
Deputy Drilled-In Anchors 12/2/2024 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 12/4/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 12/13/2024 Approved MICHAEL ALLEN
Drywall Nailing 12/13/2024 Approved MICHAEL ALLEN
Final 12/13/2024 Corrections Issued MICHAEL ALLEN
Smoke Detectors 12/13/2024 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Final 12/17/2024 Approved MICHAEL ALLEN
Final 12/17/2024 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 12/17/2024 Approved MICHAEL ALLEN
Smoke Detectors 12/17/2024 Approved MICHAEL ALLEN