7221 S OGELSBY AVE 90045
Certificate Information: 7221 S OGELSBY AVE 90045
- Application / Permit
- 24014-20000-03144
- Plan Check / Job No.
- B24VN10152
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (15'-0"x10'-0"), 150 SQFT ADDITION OF A SUNROOM/PATIO COVER PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | PETER MOSESIAN |
| Corrections Issued | 7/27/2024 | PETER MOSESIAN |
| Quality Review Completed | 7/31/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 8/1/2024 | APPLICANT |
| Plan Check Approved | 10/4/2024 | PETER MOSESIAN |
| Issued | 10/4/2024 | APPLICANT |
| CofO in Progress | 12/18/2024 | MICHAEL ALLEN |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
| CofO Issued | 12/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 10/2/2024 | HAMID GHAEMMAGHAMI |
Contact Information
| Contractor | Right Choice Home Remodeling Inc The; Lic. No.: 1066456-B | 15315 MAGNOLIA BLVD #429 SHERMAN OAKS, CA 91403 |
| Engineer | Hofmann,, Jeffrey Erwin; Lic. No.: C47407 | 9198 GREENBACK LN #116 ORANGEVALE, CA 95662 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/5/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Drywall Nailing | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Final | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Footing/Foundation/Slab | 11/7/2024 | Corrections Issued | MICHAEL ALLEN |
| METHANE-Barrier | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| METHANE-Final | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| METHANE-Subgrade | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Smoke Detectors | 11/7/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Special/Order Compliance | 11/7/2024 | Partial Inspection | HERBERT GIRON |
| Deputy Drilled-In Anchors | 12/2/2024 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 12/4/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 12/13/2024 | Approved | MICHAEL ALLEN |
| Final | 12/13/2024 | Corrections Issued | MICHAEL ALLEN |
| Smoke Detectors | 12/13/2024 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Final | 12/17/2024 | Approved | MICHAEL ALLEN |
| Final | 12/17/2024 | OK to Issue CofO | MICHAEL ALLEN |
| HVAC-Final | 12/17/2024 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 12/17/2024 | Approved | MICHAEL ALLEN |