10233 N LEMONA AVE 91345

Certificate Information: 10233 N LEMONA AVE 91345

Application / Permit
24014-20000-03142
Plan Check / Job No.
B24VN10148
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX RECREATION ROOM W/ ATTACHED BATHROOM (FOR POOL) INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH ADDITION. SEE COMMENTS.
Permit Issued
Issued on 10/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2024 APPLICANT
Assigned to Plan Check Engineer 7/24/2024 HAYATO TSUCHIYA
Corrections Issued 7/24/2024 HAYATO TSUCHIYA
Building Plans Picked Up 7/25/2024 APPLICANT
Applicant returned to address corrections 9/13/2024 HAYATO TSUCHIYA
Plan Check Approved 9/20/2024 YAQUB MIRZA
Issued 10/2/2024 APPLICANT
CofO in Progress 1/22/2025 JENNIFER RABUCHIN
Permit Finaled 1/28/2025 RUBEN SALAS
CofO Issued 1/28/2025 RUBEN SALAS
Permit Finaled 1/28/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/10/2024 EDGAR ALCARAZ
Address approval Cleared 9/11/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 9/12/2024 EDGAR ALCARAZ
Sewer availability Cleared 9/12/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/22/2024 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 10/22/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/25/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/4/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 11/4/2024 Not Ready for Inspection JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 11/21/2024 Corrections Issued JENNIFER RABUCHIN
Insulation 12/2/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/2/2024 Partial Approval JENNIFER RABUCHIN
Shower Pan 12/2/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 12/6/2024 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 12/6/2024 Approved JOSE AVILA
Drywall Nailing 12/11/2024 Approved JENNIFER RABUCHIN
Green Building Rough 12/11/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/15/2025 Approved JENNIFER RABUCHIN
Final 1/15/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/15/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/15/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/17/2025 Approved JENNIFER RABUCHIN
Final 1/17/2025 Partial Approval JENNIFER RABUCHIN
HVAC-Final 1/17/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/17/2025 Approved JENNIFER RABUCHIN
Final 1/23/2025 OK to Issue CofO JENNIFER RABUCHIN