7900 N MAYNARD AVE 91304
Certificate Information: 7900 N MAYNARD AVE 91304
- Application / Permit
- 24014-20000-03139
- Plan Check / Job No.
- B24VN10131
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN ADDITION OF (N) FAMILY ROOM TO THE REAR OF (E) SFD. REMOVE ATTACHED PATIO COVER IN THE SAME LOCATION
- Permit Issued
- Issued on 7/31/2024
- Issuing Office
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | JOHNPAUL ISIP |
| Corrections Issued | 7/23/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 7/30/2024 | JOHNPAUL ISIP |
| Issued | 7/31/2024 | APPLICANT |
| CofO in Progress | 10/9/2024 | JEFFREY HARTLINE |
| Permit Finaled | 10/25/2024 | JOHN JANSON |
| CofO Issued | 10/25/2024 | JOHN JANSON |
| Permit Finaled | 10/25/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/9/2024 | Conditional Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 8/9/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 8/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 8/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Special/Order Compliance | 8/20/2024 | Approved | SCOTT SOBEL |
| Wood Frame | 8/20/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Rough | 8/26/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 8/26/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 9/3/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 9/3/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 9/6/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 9/6/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 9/10/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 9/16/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/16/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 9/16/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 9/16/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 9/18/2024 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/25/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 10/2/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 10/2/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 10/2/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 10/8/2024 | Approved | JEFFREY HARTLINE |
| Final | 10/8/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| HVAC-Final | 10/8/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 10/8/2024 | Approved | JEFFREY HARTLINE |