6443 N CHARLESWORTH AVE 91606
Certificate Information: 6443 N CHARLESWORTH AVE 91606
- Application / Permit
- 24014-20000-03117
- Plan Check / Job No.
- B24VN10079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND (N) ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (e). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2024 | MADISON ODELL |
| Corrections Issued | 7/24/2024 | MADISON ODELL |
| Applicant returned to address corrections | 1/15/2025 | KAMYAR EMAMI |
| Plan Check Approved | 1/27/2025 | MADISON O'DELL |
| Issued | 2/3/2025 | APPLICANT |
| CofO in Progress | 9/3/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/27/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/28/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 12/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/11/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 2/11/2025 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 2/24/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 2/25/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 3/20/2025 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/11/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/11/2025 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 4/11/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/16/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/23/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/25/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/29/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/2/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/16/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Shower Pan | 5/16/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/20/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 8/25/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 8/27/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 8/27/2025 | Approved | WAYNE REGESTER |
| Final | 9/2/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |