4140 N ELMER AVE 91602
Certificate Information: 4140 N ELMER AVE 91602
- Application / Permit
- 24014-20000-03101
- Plan Check / Job No.
- B24VN10022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Interior remodel and ground floor addition to an existing one story single family dwelling R3 occupancy
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | KELVIN CHUONG |
| Corrections Issued | 7/23/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/29/2024 | KELVIN CHUONG |
| Plan Check Approved | 7/31/2024 | KELVIN CHUONG |
| Issued | 8/1/2024 | APPLICANT |
| CofO in Progress | 7/25/2025 | JAVIER RAMOS JR |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 7/23/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 7/23/2024 | KEVIN CHUNG |
| ZI | Cleared | 7/24/2024 | RUBEN VASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 8/13/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 9/9/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 9/13/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 9/13/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 10/3/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 10/24/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/5/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/5/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/5/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/12/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/4/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 12/10/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/10/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/30/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/15/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/30/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 5/30/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 6/12/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 6/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 6/12/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 6/12/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 6/12/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/13/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 6/13/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 6/13/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 6/13/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/25/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 7/25/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/25/2025 | Approved | JAVIER RAMOS JR |