10545 N HAYVENHURST AVE 91344
Certificate Information: 10545 N HAYVENHURST AVE 91344
- Application / Permit
- 24014-20000-03095
- Plan Check / Job No.
- B24VN10006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 19' x 21'4" ADDITION TO (E) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/26/2024
- Issuing Office
- Valley
- Current Status
- Issued on 8/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 7/23/2024 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 7/29/2024 | APPLICANT |
| Issued | 8/26/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/9/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/12/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/27/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 6/13/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 6/16/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 6/23/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/3/2025 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 7/28/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/28/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 8/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 8/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 8/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 9/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 9/15/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 9/17/2025 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 9/17/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/25/2025 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Insulation | 10/3/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/23/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/14/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 11/14/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/17/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 7/17/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 7/17/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/17/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/17/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/17/2026 | Approved | CHRISTOPHER ROJAS |