11312 N HAYVENHURST AVE 91344

Certificate Information: 11312 N HAYVENHURST AVE 91344

Application / Permit
24014-20000-03093
Plan Check / Job No.
B24VN09987
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH 12' x 20' ADDITION TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 12/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/23/2024 MIROOSH KHACHATOORIAN
Corrections Issued 7/23/2024 MIROOSH KHACHATOORIAN
Building Plans Picked Up 7/24/2024 APPLICANT
Plan Check Approved 12/13/2024 DANIEL ABRAMYAN
Issued 12/19/2024 APPLICANT
CofO in Progress 6/25/2025 CHRISTOPHER ROJAS
Permit Finaled 7/1/2025 RUBEN SALAS
CofO Issued 7/1/2025 RUBEN SALAS
Permit Finaled 7/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/26/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 7/26/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/1/2024 RYAN CASTRO
Sewer availability Cleared 8/1/2024 RYAN CASTRO
Construction near power lines Cleared 11/2/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/6/2024 MANUEL TEJADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/20/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/27/2025 Conditional Approval KEVIN BERBERYAN
PLUMBING-Rough 1/27/2025 Partial Approval KEVIN BERBERYAN
Underground Mechanical 1/27/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Partial Approval RAUL OLAGI
Sewer 2/24/2025 Approved RAUL OLAGI
Underground Mechanical 2/24/2025 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/28/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/7/2025 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 3/7/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/15/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/15/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 4/15/2025 Partial Inspection CHRISTOPHER ROJAS
HVAC-Rough 4/15/2025 Partial Inspection CHRISTOPHER ROJAS
MERV13>=Rough 4/15/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 4/15/2025 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/23/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/23/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 4/23/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 4/23/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 4/23/2025 Approved NICHOLAS TROWBRIDGE
Insulation 4/28/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/1/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 5/5/2025 Approved LOUIS ESCOTO
Final 6/17/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/17/2025 Approved CHRISTOPHER ROJAS
Green Building Final 6/17/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 6/17/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/17/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 6/17/2025 Approved CHRISTOPHER ROJAS
Final 6/24/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 6/24/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 6/24/2025 Approved CHRISTOPHER ROJAS