8656 N NORRIS AVE 91352
Certificate Information: 8656 N NORRIS AVE 91352
- Application / Permit
- 24014-20000-03070
- Plan Check / Job No.
- B24VN09911
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: GARAGE CONVERSION INTO (N) ADU WITH ADDITION ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2024 | SUNMIN LEE |
| Corrections Issued | 7/25/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 9/12/2024 | SUNMIN LEE |
| Plan Check Approved | 9/18/2024 | DANIEL SANJUAN |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 11/13/2025 | DAVID ANDERSON |
| Permit Finaled | 12/12/2025 | RUBEN SALAS |
| CofO Issued | 12/12/2025 | RUBEN SALAS |
| Permit Finaled | 12/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 8/12/2024 | KEVIN CHUNG |
| Clean Up Green Up | Cleared | 8/15/2024 | ALEX VELA |
| ZI | Cleared | 8/15/2024 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 9/3/2024 | KEVIN CHUNG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: NA70784 | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/12/2024 | Partial Inspection | RYAN SALAZAR |
| Pre-Inspection | 11/19/2024 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Corrections Issued | DAVID ANDERSON |
| Special/Order Compliance | 11/26/2024 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 12/3/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 12/9/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/13/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 12/13/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/16/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 12/27/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 12/27/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/27/2024 | No Access for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/27/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 12/27/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Sewer | 12/27/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 12/27/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/30/2024 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 12/30/2024 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 12/30/2024 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/30/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/30/2024 | Partial Inspection | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 1/3/2025 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/13/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/13/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 1/13/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 1/13/2025 | Approved | DAVID ANDERSON |
| Wood Frame | 1/13/2025 | Approved | DAVID ANDERSON |
| Insulation | 1/15/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 1/17/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/21/2025 | Corrections Issued | MICHAEL CORTEZ |
| Drywall Nailing | 1/22/2025 | Approved | DAVID ANDERSON |
| Final | 3/5/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/5/2025 | Approved | DAVID ANDERSON |
| Green Building Final | 3/5/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 3/5/2025 | Approved | DAVID ANDERSON |
| Final | 3/7/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/17/2025 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/10/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Gas Test | 9/10/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 10/29/2025 | Approved | DAVID ANDERSON |
| Final | 11/12/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 11/12/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | DAVID ANDERSON |