12426 W WOODGREEN ST 90066

Certificate Information: 12426 W WOODGREEN ST 90066

Application / Permit
24014-20000-03032
Plan Check / Job No.
B24VN09786
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major Remodel, Extend Patio Cover at Entrance, (40' x 34'-5" Irregular Shape) Addition and Addition of (25' x 8') Patio Cover to existing 1-Story Single Family Dwelling. NFPA 13D Fire Sprinklers Throughout.
Permit Issued
Issued on 1/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 VAHAN JIVALAGIAN
Corrections Issued 7/21/2024 VAHAN JIVALAGIAN
Quality Review Completed 7/25/2024 OMID HEDAYAT
Building Plans Picked Up 8/2/2024 APPLICANT
Applicant returned to address corrections 10/25/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/6/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/20/2024 VAHAN JIVALAGIAN
Issued 1/7/2025 APPLICANT
CofO in Progress 2/12/2026 MICHAEL ALLEN
Permit Finaled 2/24/2026 RICHARD STEINBACH
CofO Issued 2/24/2026 RICHARD STEINBACH
Permit Finaled 2/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/11/2024 DARIN LAM
Sewer availability Cleared 10/11/2024 DARIN LAM
Grading Pre-Inspection Cleared 10/15/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 10/21/2024 DARIN LAM
GPI Written Notices Cleared 11/20/2024 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2025 Approved MICHAEL ALLEN
Deputy Reinf. Concrete 5/1/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 5/19/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 8/26/2025 Approved WILBER ROSALES
HVAC-Rough 8/26/2025 Approved WILBER ROSALES
PLUMBING-Rough 8/26/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 9/8/2025 Approved WILBER ROSALES
Green Building Rough 9/8/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/8/2025 Approved WILBER ROSALES
Insulation 9/12/2025 Corrections Issued WILBER ROSALES
Insulation 9/15/2025 Approved WILBER ROSALES
Shower Pan 9/15/2025 Approved WILBER ROSALES
Drywall Nailing 9/22/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/22/2025 Approved WILBER ROSALES
Gas Test 12/9/2025 Approved WILBER ROSALES
Sewer 12/9/2025 Approved WILBER ROSALES
Underground Mechanical 12/9/2025 Approved WILBER ROSALES
ELECTRICAL-Final 2/4/2026 Approved HERBERT GIRON
Gas Test 2/4/2026 Approved HERBERT GIRON
HVAC-Final 2/4/2026 Approved HERBERT GIRON
PLUMBING-Final 2/4/2026 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/9/2026 Approved ANTHONY EGSON
Final 2/11/2026 OK to Issue CofO MICHAEL ALLEN
Footing/Foundation/Slab 2/11/2026 Approved MICHAEL ALLEN
Green Building Final 2/11/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 2/11/2026 Approved MICHAEL ALLEN