22932-22934 W VALERIO ST 91307
Certificate Information: 22932-22934 W VALERIO ST 91307
- Application / Permit
- 24014-20000-03025
- Plan Check / Job No.
- B24VN09778
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREG SHAPED ADDITION TO AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- Valley
- Current Status
- Issued on 11/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 7/20/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/30/2024 | APPLICANT |
| Plan Check Approved | 11/21/2025 | GIOVANNY CHAVEZ |
| Issued | 11/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/7/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/21/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 1/22/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 1/28/2026 | Partial Approval | JEFFREY HARTLINE |
| Pre-Inspection | 1/28/2026 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 1/28/2026 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/4/2026 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 3/4/2026 | Approved | JEFFREY HARTLINE |
| Wood Frame | 3/4/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 3/9/2026 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 3/9/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 3/9/2026 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2026 | Partial Approval | TROY SANDERS |
| Insulation | 3/13/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/13/2026 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 3/17/2026 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 3/24/2026 | Approved | JEFFREY HARTLINE |
| Shower Pan | 4/17/2026 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 4/22/2026 | Approved | JEFFREY HARTLINE |