12142 W EMELITA ST 91607
Certificate Information: 12142 W EMELITA ST 91607
- Application / Permit
- 24014-20000-03022
- Plan Check / Job No.
- B24VN09766
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Major remodel and addition of irregular shaped 69' 2 1/16" x 61' on the South side of the lot, 32.67 SF addition on the West side of the lot, and 155.4 SF addition on the North side of the lot to the single family dwelling, with attached garage, trellis, porch and patio cover, total footprint of Single Family Dwelling is 94' 2" x 63'. NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 11/1/2024
- Issuing Office
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | NAREG ATARIAN |
| Corrections Issued | 7/20/2024 | NAREG ATARIAN |
| Quality Review Completed | 7/23/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/5/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/4/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/24/2024 | NAREG ATARIAN |
| Plan Check Approved | 10/31/2024 | NAREG ATARIAN |
| Issued | 11/1/2024 | APPLICANT |
| CofO in Progress | 8/27/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
| CofO Issued | 9/5/2025 | RUBEN SALAS |
| Permit Finaled | 9/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Susan Development And Construction Inc; Lic. No.: 1089492-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 12/31/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/31/2024 | Approved | KEVIN BERBERYAN |
| Deputy Reinf. Concrete | 1/2/2025 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 1/23/2025 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 1/23/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/19/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/19/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 3/19/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/19/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/19/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/19/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 3/25/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 3/26/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/26/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/26/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/1/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/14/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 7/1/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Service/Power Release | 7/18/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/1/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/11/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 8/11/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Final | 8/11/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 8/11/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/11/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/11/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/11/2025 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 8/12/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 8/26/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |