10325 N SILVERTON AVE 91042

Certificate Information: 10325 N SILVERTON AVE 91042

Application / Permit
24014-20000-03000
Plan Check / Job No.
B24VN09686
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 23'-5"X23'-2" ADDITION OF COVERED DECK W/ STORAGE BELOW
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 JESSE ARELLANO
Corrections Issued 7/13/2024 JESSE ARELLANO
Building Plans Picked Up 7/18/2024 APPLICANT
Applicant returned to address corrections 10/15/2024 KAMYAR EMAMI
Issued 10/17/2024 APPLICANT
CofO in Progress 9/4/2025 WILLIAM WREN
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/15/2024 CARLOS AGUILERA
GPI Written Notices Cleared 10/15/2024 JESSE ARELLANO
Grading Pre-Inspection Cleared 10/15/2024 JESSE ARELLANO
Roof/Waste drainage to street Cleared 10/15/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/27/2024 Corrections Issued WILLIAM WREN
Pre-Inspection 1/15/2025 Partial Inspection WILLIAM WREN
Deputy Drilled-In Anchors 2/27/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 2/27/2025 Approved WILLIAM WREN
Reinforced Masonry Frame 3/5/2025 Approved WILLIAM WREN
Pre-Inspection 3/7/2025 Not Ready for Inspection WILLIAM WREN
Reinforced Masonry Frame 3/7/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 3/19/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/28/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 4/10/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 4/10/2025 Not Ready for Inspection WILLIAM WREN
Green Building Rough 4/10/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 4/29/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 4/29/2025 Approved WILLIAM WREN
Insulation 5/7/2025 Approved WILLIAM WREN
Shower Pan 5/7/2025 Approved WILLIAM WREN
Drywall Nailing 5/16/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/12/2025 Approved WILLIAM WREN
Final 8/12/2025 OK to Issue CofO WILLIAM WREN
Footing/Foundation/Slab 8/12/2025 Approved WILLIAM WREN
Green Building Final 8/12/2025 Approved WILLIAM WREN
Green Building Rough 8/12/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 8/12/2025 Approved WILLIAM WREN