- 16'-6" X 15'-0" ADDITION TO & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 7/13/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/15/2024 | APPLICANT |
| Plan Check Approved | 8/28/2024 | ALEC MOUSAKHANIAN |
| Issued | 8/28/2024 | APPLICANT |
| CofO in Progress | 7/7/2025 | STEVEN BACK |
| CofO Issued | 7/21/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/23/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 7/24/2024 | CHARLES POWELL |
| Construction near power lines | Cleared | 8/20/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/9/2024 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 10/21/2024 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 10/28/2024 | Approved | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 10/28/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 10/28/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 12/18/2024 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 1/24/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 1/24/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 1/24/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 2/11/2025 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | STEVEN BACK |
| Green Building Rough | 2/24/2025 | Approved | STEVEN BACK |
| Insulation | 2/24/2025 | Approved | STEVEN BACK |
| MERV13>=Rough | 2/24/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 2/27/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 2/27/2025 | Approved | STEVEN BACK |
| Shower Pan | 3/13/2025 | No Access for Inspection | STEVEN BACK |
| Sewer | 3/20/2025 | Approved | STEVEN BACK |
| Underground Mechanical | 3/20/2025 | Approved | STEVEN BACK |
| Shower Pan | 4/1/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 4/4/2025 | Approved | SCOTT SOBEL |
| Green Building Final | 5/28/2025 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | STEVEN BACK |
| ELECTRICAL-Final | 5/30/2025 | Corrections Issued | JEFFREY PARD |
| Gas Test | 5/30/2025 | Approved | JEFFREY PARD |
| HVAC-Final | 5/30/2025 | Approved | JEFFREY PARD |
| PLUMBING-Final | 5/30/2025 | Corrections Issued | JEFFREY PARD |
| Service/Power Release | 5/30/2025 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 6/3/2025 | Approved | STEVEN BACK |
| Final | 6/3/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/3/2025 | Approved | STEVEN BACK |
| HVAC-Final | 6/3/2025 | Approved | STEVEN BACK |
| MERV13>=Final | 6/3/2025 | Approved | STEVEN BACK |
| PLUMBING-Final | 6/3/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 6/3/2025 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 6/3/2025 | Approved | STEVEN BACK |
| Final | 6/9/2025 | Corrections Issued | STEVEN BACK |
| Service/Power Release | 6/9/2025 | Approved | STEVEN BACK |
| Final | 6/23/2025 | Corrections Issued | STEVEN BACK |
| Final | 7/7/2025 | OK to Issue CofO | STEVEN BACK |
| Special/Order Compliance | 7/7/2025 | Approved | STEVEN BACK |