14515-14517 W DUCAT ST 91345

Certificate Information: 14515-14517 W DUCAT ST 91345

Application / Permit
24014-20000-02988
Plan Check / Job No.
B24VN09657
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ATTACHED GARAGE CONVERSION TO ADU WITH ADDITION PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 9/10/2024
Issuing Office
Current Status
CofO Issued on 2/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 GURUNATH NESARAJAH
Corrections Issued 7/13/2024 GURUNATH NESARAJAH
Plan Check Approved 9/6/2024 GURUNATH NESARAJAH
Issued 9/10/2024 APPLICANT
CofO in Progress 8/8/2025 MISAEL ESPARZA
Permit Finaled 2/14/2026 MICHAEL PELHAM
Permit Finaled 2/14/2026 MICHAEL PELHAM
CofO Issued 2/14/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 7/20/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/20/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 8/12/2024 EDGAR ALCARAZ
Sewer availability Cleared 8/12/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2024 Approved JENNIFER RABUCHIN
METHANE-Barrier 10/17/2024 Approved JENNIFER RABUCHIN
METHANE-Subgrade 10/17/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/11/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Approved JENNIFER RABUCHIN
Green Building Rough 12/11/2024 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 12/11/2024 Approved JENNIFER RABUCHIN
METHANE-Rough 12/11/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/26/2024 Approved JENNIFER RABUCHIN
Gas Test 12/26/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Final 12/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/26/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/7/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 1/7/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/7/2025 Approved CHRISTOPHE COCHRAN
Insulation 1/27/2025 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 2/12/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 2/18/2025 Approved JENNIFER RABUCHIN
Insulation 2/18/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/18/2025 Approved JENNIFER RABUCHIN
Shower Pan 2/18/2025 Approved JENNIFER RABUCHIN
Pre-Inspection 2/25/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/15/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/15/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/15/2025 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 7/15/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/15/2025 Approved JENNIFER RABUCHIN
Final 7/28/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/28/2025 Approved JENNIFER RABUCHIN
Final 8/6/2025 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 8/8/2025 Approved MISAEL ESPARZA