7332 N SYLVIA AVE 91335

Certificate Information: 7332 N SYLVIA AVE 91335

Application / Permit
24014-20000-02982
Plan Check / Job No.
B24VN09649
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) FRONT AND REAR ADDITION TO (E) SINGLE-FAMILY DWELLING AND (N) FRONT PORCH
Permit Issued
Issued on 10/2/2024
Issuing Office
Valley
Current Status
CofO in Progress on 1/21/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/9/2024 ALEC MOUSAKHANIAN
Corrections Issued 7/9/2024 ALEC MOUSAKHANIAN
Plan Check Approved 10/2/2024 YAQUB MIRZA
Issued 10/2/2024 APPLICANT
CofO in Progress 1/21/2026 ARUTYUN MADATYAN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/29/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 9/5/2024 CARLOS RAMIREZ
Sewer availability Cleared 9/5/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/18/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 11/27/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 12/10/2024 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 12/10/2024 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 12/12/2024 Partial Approval ALEXANDER HANDY
Insulation 12/12/2024 Partial Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 12/30/2024 Partial Approval SCOTT SOBEL
ELECTRICAL-Rough 1/28/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Approved ARUTYUN MADATYAN
Green Building Rough 1/28/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 1/28/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/10/2025 Approved JUAN ALVARADO
Green Building Rough 2/10/2025 Approved JUAN ALVARADO
Insulation 2/10/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/10/2025 Corrections Issued JUAN ALVARADO
PLUMBING-Rough 2/10/2025 Approved JUAN ALVARADO
Drywall Nailing 2/26/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/26/2025 Approved JUAN ALVARADO
Shower Pan 3/14/2025 Approved JUAN ALVARADO
PLUMBING-Rough 3/20/2025 Approved JUAN ALVARADO
Shower Pan 3/20/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 7/7/2025 Corrections Issued ROBERT GOLD
Wood Frame 7/7/2025 Partial Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 7/10/2025 Approved ROBERT GOLD
Footing/Foundation/Slab 7/10/2025 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Approved JUAN ALVARADO
Wood Frame 7/28/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 8/1/2025 Approved JUAN ALVARADO
Final 9/25/2025 Corrections Issued JUAN ALVARADO
Green Building Final 9/25/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 9/25/2025 Approved JUAN ALVARADO
Final 10/8/2025 Corrections Issued JUAN ALVARADO
Final 12/1/2025 Partial Approval JUAN ALVARADO
ELECTRICAL-Final 1/20/2026 Approved ARUTYUN MADATYAN
Final 1/20/2026 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 1/20/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 1/20/2026 Approved ARUTYUN MADATYAN