NEW 6'8" X 19'2" IRREGULAR SHAPED ADDITION TO (E) 2ND FLOOR FOR NEW BEDROOM AND BATHROOM, NEW 5'9" X 2'9" ADDITION AT 2ND FLOOR TO ENLARGE THE BATHROOM AND INTERIOR REMODEL AT 1ST AND 2ND FLOOR , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 RARES BODEA
Corrections Issued 7/16/2024 RARES BODEA
Quality Review Completed 7/18/2024 STEVEN KIM
Building Plans Picked Up 7/22/2024 APPLICANT
Applicant returned to address corrections 12/5/2024 RARES BODEA
Plan Check Approved 1/6/2025 RARES BODEA
Issued 1/6/2025 APPLICANT
CofO in Progress 5/5/2026 HERBERT GIRON
Permit Finaled 5/11/2026 RICHARD STEINBACH
CofO Issued 5/11/2026 RICHARD STEINBACH
Permit Finaled 5/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/24/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 7/24/2024 VLADIMIR ARUTYUNYAN
Watercourse Cleared 7/24/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 7/25/2024 HISASHI KOBAYAKAWA
Certificate of Compliance Cleared 11/26/2024 DAVID URITA
Coastal Zone Cleared 11/26/2024 DAVID URITA
Grading Pre-Inspection Cleared 12/5/2024 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/29/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/27/2025 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Partial Approval JESUS RODRIGUEZ
Green Building Rough 2/27/2025 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 2/27/2025 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 3/21/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Approved HERBERT GIRON
PLUMBING-Rough 3/21/2025 Approved HERBERT GIRON
HVAC-Rough 7/23/2025 Corrections Issued HERBERT GIRON
Shower Pan 7/23/2025 Approved HERBERT GIRON
Insulation 7/25/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 8/11/2025 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 8/11/2025 Partial Approval HERBERT GIRON
Final 8/11/2025 Corrections Issued HERBERT GIRON
Green Building Rough 8/11/2025 Approved HERBERT GIRON
HVAC-Rough 8/11/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 8/11/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 9/16/2025 Corrections Issued HERBERT GIRON
Insulation 9/16/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 9/16/2025 Partial Approval HERBERT GIRON
Insulation 10/16/2025 Partial Approval HERBERT GIRON
Drywall Nailing 10/21/2025 Partial Approval HERBERT GIRON
HVAC-Rough 10/21/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 10/28/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 11/4/2025 Approved HERBERT GIRON
Drywall Nailing 11/4/2025 Approved HERBERT GIRON
ELECTRICAL-Rough 11/4/2025 Approved HERBERT GIRON
Insulation 11/4/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 11/4/2025 Approved HERBERT GIRON
ELECTRICAL-Final 2/20/2026 Corrections Issued HERBERT GIRON
PLUMBING-Final 2/20/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/9/2026 Approved HERBERT GIRON
HVAC-Final 3/9/2026 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/9/2026 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved HERBERT GIRON
Service/Power Release 3/9/2026 Approved HERBERT GIRON
HVAC-Final 3/18/2026 Approved HERBERT GIRON
Special/Order Compliance 3/18/2026 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 3/23/2026 Conditional Approval JUAN VALENZUELA
Pre-Inspection 4/2/2026 Approved JUAN VALENZUELA
Final 5/5/2026 OK to Issue CofO HERBERT GIRON
Green Building Final 5/5/2026 Approved HERBERT GIRON
Smoke Detectors 5/5/2026 Approved HERBERT GIRON