10944-10946 N ETIWANDA AVE 91326

Certificate Information: 10944-10946 N ETIWANDA AVE 91326

Application / Permit
24014-20000-02978
Plan Check / Job No.
B24VN09637
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN GARAGE 420.0 S.F., PART OF SFD 304 S.F., AND 2ND STORY 441.0 S.F. CONVERT TO NEW ADU. ADU TOTAL:1,135.5 S.F. PER STATE LAW NEW PATIO 200.0 S.F.
Permit Issued
Issued on 10/14/2024
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 KHUONG TRUONG
Corrections Issued 8/5/2024 KHUONG TRUONG
Quality Review Completed 8/6/2024 GARO TELMI
Plan Check Approved 8/16/2024 KHUONG TRUONG
Issued 10/14/2024 APPLICANT
CofO in Progress 4/3/2025 DAVID SCANTLIN
Permit Finaled 4/14/2025 JOHN JANSON
CofO Issued 4/14/2025 JOHN JANSON
Permit Finaled 4/14/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/5/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/5/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/14/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/14/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/9/2025 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 1/10/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 1/24/2025 Approved DAVID SCANTLIN
Insulation 1/28/2025 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 1/31/2025 Approved DAVID SCANTLIN
Drywall Nailing 2/10/2025 Partial Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 2/19/2025 Corrections Issued SEAN WIRCH
ELECTRICAL-Final 2/27/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 2/27/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/24/2025 Approved DAVID SCANTLIN
Final 3/24/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 3/24/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 3/24/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 3/24/2025 Not Ready for Inspection DAVID SCANTLIN
Final 4/2/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 4/2/2025 Approved DAVID SCANTLIN
Smoke Detectors 4/2/2025 Approved DAVID SCANTLIN
Service/Power Release 4/11/2025 Approved DAVID SCANTLIN