8144-8146 N ETIWANDA AVE 91335

Certificate Information: 8144-8146 N ETIWANDA AVE 91335

Application / Permit
24014-20000-02962
Plan Check / Job No.
B24VN09583
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ENCLOSE AND CONVERT PATIO COVER TO ENLARGE DINING ROOM AND LIVING ROOM. REMODEL AND RELOCATE (E) BATHROOM. REMODEL (E) KITCHEN.
Permit Issued
Issued on 7/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 JEROME MAGAT PALMA
Corrections Issued 7/13/2024 JEROME MAGAT PALMA
Building Plans Picked Up 7/16/2024 APPLICANT
Issued 7/23/2024 APPLICANT
CofO in Progress 2/12/2025 ARUTYUN MADATYAN
Permit Finaled 3/20/2025 JOHN JANSON
CofO Issued 3/20/2025 JOHN JANSON
Permit Finaled 3/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/17/2024 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/17/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/18/2024 MARKOS PEREZ-BRAN

Contact Information

Architect Koch,, Richard W; Lic. No.: C13782 5920 PALOMAR CIRCLE      CAMARILLO, CA 930127131
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/13/2024 Conditional Approval JEFFREY BULL
Excavation/Setback/Form/Re-Bar 8/21/2024 Approved JEFFREY BULL
PLUMBING-Rough 9/10/2024 Not Ready for Inspection JEFFREY BULL
Shower Pan 9/10/2024 Approved JEFFREY BULL
Wood Frame 9/10/2024 Approved JEFFREY BULL
Deputy Wood Construction 9/20/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 9/20/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Approved JEFFREY BULL
PLUMBING-Rough 9/20/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 9/26/2024 Approved JEFFREY BULL
Drywall Nailing 10/1/2024 Partial Approval KRISTEN CAUSEY
Insulation 10/1/2024 Approved KRISTEN CAUSEY
Drywall Nailing 10/9/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/27/2025 Approved ARUTYUN MADATYAN
Final 1/27/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 1/27/2025 Approved ARUTYUN MADATYAN
Green Building Final 1/27/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 1/27/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 1/27/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/11/2025 Approved ARUTYUN MADATYAN
Final 2/11/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 2/11/2025 Approved ARUTYUN MADATYAN
HVAC-Final 2/11/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 2/11/2025 Approved ARUTYUN MADATYAN
Service/Power Release 2/11/2025 Approved ARUTYUN MADATYAN