7926 N NORTHGATE AVE 91304

Certificate Information: 7926 N NORTHGATE AVE 91304

Application / Permit
24014-20000-02952
Plan Check / Job No.
B24VN09562
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN New Addition (92 SF) of Existing SFD and ADU.
Permit Issued
Issued on 8/4/2024
Issuing Office
Current Status
CofO in Progress on 3/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 TSE MING HUANG
Corrections Issued 7/12/2024 TSE MING HUANG
Plan Check Approved 8/2/2024 TSE MING HUANG
Issued 8/4/2024 APPLICANT
CofO in Progress 4/14/2025 ALEXANDER HANDY
No Progress 3/5/2026 ROBERT GOLD
CofO in Progress 3/5/2026 ROBERT GOLD

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/16/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/16/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/17/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/7/2024 Conditional Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 10/17/2024 Corrections Issued ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 10/22/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 11/12/2024 Partial Approval ALEXANDER HANDY
Sewer 11/12/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval JEFFREY HARTLINE
Green Building Rough 12/13/2024 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 12/13/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/7/2025 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 1/7/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 1/7/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 1/7/2025 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 1/7/2025 Partial Approval ALEXANDER HANDY
Shower Pan 1/7/2025 Partial Approval ALEXANDER HANDY
Insulation 1/9/2025 Partial Approval JOHN COLEMAN
Interior/Exterior Lathing 1/15/2025 No Access for Inspection MORRIS JACKSON
Interior/Exterior Lathing 1/17/2025 Approved SCOTT SOBEL
PLUMBING-Rough 2/12/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 2/20/2025 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 4/8/2025 Approved JUAN ALVARADO
Final 4/8/2025 Not Ready for Inspection JUAN ALVARADO
Footing/Foundation/Slab 4/8/2025 Approved JUAN ALVARADO
Green Building Final 4/8/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 4/8/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Final 4/14/2025 Approved ALEXANDER HANDY
Final 4/14/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 4/14/2025 Approved ALEXANDER HANDY
PLUMBING-Final 4/14/2025 Approved ALEXANDER HANDY
Smoke Detectors 4/14/2025 Approved ALEXANDER HANDY