REMOVE (E) 1036 SF WITH 10 FEET OF WALL AND FOUNDATION TO REMAIN ON THE NORTHEAST PORTION. REBUILD 30' X 80' IRREGULAR SHAPED 2-STORY SFD W/ 2- CAR GARAGE AND TRELLIS PATIO. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/24/2024
Issuing Office
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 RAPHAEL ROSAS
Corrections Issued 7/16/2024 RAPHAEL ROSAS
Quality Review Completed 7/16/2024 STEVEN KIM
Building Plans Picked Up 7/22/2024 APPLICANT
Applicant returned to address corrections 10/17/2024 RAPHAEL ROSAS
Plan Check Approved 10/24/2024 RAPHAEL ROSAS
Issued 10/24/2024 APPLICANT
CofO in Progress 3/2/2026 MICHAEL ALLEN
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 8/5/2024 BRENDEN HAWK
Specific Plan Cleared 8/5/2024 HAMID GHAEMMAGHAMI
Roof/Waste drainage to street Cleared 8/6/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 8/11/2024 BRENDEN HAWK
Sewer availability Cleared 8/11/2024 BRENDEN HAWK
Trees in Parkway Cleared 8/26/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 10/8/2024 KURT CORRAL

Contact Information

Contractor Gaudenti & Sons Corporation; Lic. No.: 283650-B 20331 MAIN ST      CARSON, CA 90745
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2024 Partial Inspection DAVID FEILER
Pre-Inspection 12/4/2024 Partial Inspection REGINA MENDEZ
Underground Mechanical 12/12/2024 Partial Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 12/13/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/18/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 12/19/2024 Approved BOBBY KEY
Special/Order Compliance 12/19/2024 Partial Inspection JAYLIN GRAVITTE
Deputy Wood Construction 5/21/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 8/13/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 8/13/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 8/13/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/13/2025 Corrections Issued JESUS RODRIGUEZ
Special/Order Compliance 8/13/2025 Partial Inspection JAYLIN GRAVITTE
Verify Sprinkler Sign Off 8/13/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/19/2025 Approved JESUS RODRIGUEZ
Green Building Rough 8/19/2025 Approved JESUS RODRIGUEZ
Insulation 8/19/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 8/19/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 9/2/2025 Approved JESUS RODRIGUEZ
Insulation 9/2/2025 Approved JESUS RODRIGUEZ
Shower Pan 9/23/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 10/22/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/18/2025 Approved JESUS RODRIGUEZ
Underground Mechanical 12/17/2025 Approved RUBEN RIVAS
Final 2/23/2026 Corrections Issued RUBEN RIVAS
Green Building Final 2/23/2026 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Approved RUBEN RIVAS
Smoke Detectors 2/23/2026 Approved RUBEN RIVAS
ELECTRICAL-Final 2/25/2026 Approved RUBEN RIVAS
HVAC-Final 2/25/2026 Approved RUBEN RIVAS
PLUMBING-Final 2/25/2026 Approved RUBEN RIVAS
Service/Power Release 2/25/2026 Approved RUBEN RIVAS
Final 2/27/2026 OK to Issue CofO MICHAEL ALLEN