9930-9932 N NOBLE AVE 91345
Certificate Information: 9930-9932 N NOBLE AVE 91345
- Application / Permit
- 24014-20000-02904
- Plan Check / Job No.
- B24VN09428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMOVE (E) 1242 SF EXCEPT FOR 9'-11" WALL AND FOUNDATION AT SOUTHERN PORTION OF (E) SFD. REBUILD 45'-3" X 64' IRREGULAR SHAPED 1-STORY DUPLEX per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | RAPHAEL ROSAS |
| Corrections Issued | 7/16/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 7/16/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/16/2024 | APPLICANT |
| Applicant returned to address corrections | 10/10/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 10/18/2024 | RAPHAEL ROSAS |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 2/23/2026 | JENNIFER RABUCHIN |
| CofO Issued | 3/24/2026 | RUBEN SALAS |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/25/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 7/29/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/29/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 7/30/2024 | BRENNEN OBETO |
| Construction near power lines | Cleared | 9/5/2024 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 10/17/2024 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/28/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 1/30/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 3/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 3/25/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 3/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/28/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/28/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/6/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 6/6/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/6/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/13/2025 | Approved | LOUIS ESCOTO |
| Insulation | 6/13/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 6/27/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/27/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/8/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 9/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 9/11/2025 | Approved | JENNIFER RABUCHIN |
| Final | 10/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Not Required | JENNIFER RABUCHIN |
| Smoke Detectors | 10/20/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/3/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/14/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/14/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/20/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 11/25/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/19/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/19/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/19/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/19/2026 | Approved | JENNIFER RABUCHIN |