9930-9932 N NOBLE AVE 91345

Certificate Information: 9930-9932 N NOBLE AVE 91345

Application / Permit
24014-20000-02904
Plan Check / Job No.
B24VN09428
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMOVE (E) 1242 SF EXCEPT FOR 9'-11" WALL AND FOUNDATION AT SOUTHERN PORTION OF (E) SFD. REBUILD 45'-3" X 64' IRREGULAR SHAPED 1-STORY DUPLEX per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/18/2024
Issuing Office
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 RAPHAEL ROSAS
Corrections Issued 7/16/2024 RAPHAEL ROSAS
Quality Review Completed 7/16/2024 STEVEN KIM
Building Plans Picked Up 7/16/2024 APPLICANT
Applicant returned to address corrections 10/10/2024 RAPHAEL ROSAS
Plan Check Approved 10/18/2024 RAPHAEL ROSAS
Issued 10/18/2024 APPLICANT
CofO in Progress 2/23/2026 JENNIFER RABUCHIN
CofO Issued 3/24/2026 RUBEN SALAS
Permit Finaled 3/24/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/16/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/25/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 7/29/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/29/2024 BIAINA HARITUNIAN
Senate Bill 9 Cleared 7/30/2024 BRENNEN OBETO
Construction near power lines Cleared 9/5/2024 WALTER RAMIREZ
Hydrant and Access approval Cleared 10/17/2024 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/28/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/30/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 1/30/2025 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 2/3/2025 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/3/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/25/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/25/2025 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 3/27/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/28/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/28/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 5/28/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 5/28/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/28/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/6/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/6/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 6/6/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/13/2025 Approved LOUIS ESCOTO
Insulation 6/13/2025 Approved LOUIS ESCOTO
Drywall Nailing 6/27/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/27/2025 Approved JENNIFER RABUCHIN
Shower Pan 7/3/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 7/8/2025 Approved JENNIFER RABUCHIN
Shower Pan 7/8/2025 Approved JENNIFER RABUCHIN
Sewer 9/11/2025 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 9/11/2025 Approved JENNIFER RABUCHIN
Final 10/20/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/20/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/20/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Not Required JENNIFER RABUCHIN
Smoke Detectors 10/20/2025 Approved JENNIFER RABUCHIN
Final 11/3/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/3/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/3/2025 Approved JENNIFER RABUCHIN
Final 11/14/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/14/2025 Approved JENNIFER RABUCHIN
Final 11/20/2025 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 11/25/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/19/2026 Approved JENNIFER RABUCHIN
Final 2/19/2026 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/19/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/19/2026 Approved JENNIFER RABUCHIN