5709 N WALLIS LANE 91367

Certificate Information: 5709 N WALLIS LANE 91367

Application / Permit
24014-20000-02889
Plan Check / Job No.
B24VN09351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) SFD AND ADD 13'-0" x 31'-5" COVERED PATIO & 13' x 27'5" OPEN TRELLIS. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 8/22/2024
Issuing Office
Current Status
CofO Issued on 4/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/8/2024 ARTIN ZARUKIAN
Corrections Issued 7/8/2024 ARTIN ZARUKIAN
Building Plans Picked Up 7/10/2024 APPLICANT
Issued 8/22/2024 APPLICANT
CofO in Progress 4/1/2025 ALEXANDER HANDY
CofO Issued 4/2/2025 JOHN JANSON
Permit Finaled 4/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/13/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/29/2024 LEE GUILBEAUX
Sewer availability Cleared 7/29/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/29/2024 LEE GUILBEAUX
ZA Case Cleared 8/20/2024 NATHAN ROMINE
Grading Pre-Inspection Cleared 8/22/2024 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 8/28/2024 Approved ARUTYUN MADATYAN
Special/Order Compliance 8/28/2024 Approved HENRY KIM
Excavation/Setback/Form/Re-Bar 9/13/2024 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 9/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
Sewer 9/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
Underground Mechanical 9/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Drilled-In Anchors 9/16/2024 Conditional Approval ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 9/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/17/2024 Partial Approval ARUTYUN MADATYAN
Sewer 9/17/2024 Approved ARUTYUN MADATYAN
Underground Mechanical 9/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 9/19/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 9/19/2024 Not Ready for Inspection JEFFREY BULL
Footing/Foundation/Slab 9/24/2024 Approved ARUTYUN MADATYAN
Gas Test 9/24/2024 Partial Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 9/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 9/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/11/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 10/11/2024 No Access for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 10/11/2024 No Access for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 10/11/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 10/17/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 10/17/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 10/17/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 10/21/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/21/2024 Partial Approval ARUTYUN MADATYAN
Wood Frame 10/21/2024 Not Ready for Inspection ARUTYUN MADATYAN
Insulation 10/31/2024 Approved ARUTYUN MADATYAN
Shower Pan 10/31/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 11/4/2024 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 11/4/2024 Not Ready for Inspection KRISTEN CAUSEY
Drywall Nailing 11/7/2024 Approved SCOTT SOBEL
Interior/Exterior Lathing 11/7/2024 Not Ready for Inspection SCOTT SOBEL
Interior/Exterior Lathing 11/13/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Final 2/28/2025 Corrections Issued ALEXANDER HANDY
Final 2/28/2025 Corrections Issued ALEXANDER HANDY
HVAC-Final 2/28/2025 Approved ALEXANDER HANDY
PLUMBING-Final 2/28/2025 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Not Ready ALEXANDER HANDY
Smoke Detectors 2/28/2025 Approved ALEXANDER HANDY
Final 3/17/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Not Ready DAVID SCANTLIN
ELECTRICAL-Final 3/28/2025 Approved ALEXANDER HANDY
Final 3/28/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 3/28/2025 Approved ALEXANDER HANDY
HVAC-Final 3/28/2025 Approved ALEXANDER HANDY
PLUMBING-Final 3/28/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/28/2025 SGSOV Approved ALEXANDER HANDY