4072 N ALONZO AVE 91316

Certificate Information: 4072 N ALONZO AVE 91316

Application / Permit
24014-20000-02885
Plan Check / Job No.
B24VN09338
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD, REMOVE REAR PATIO & STORAGE ROOM AND ENCLOSE FRONT PORCH
Permit Issued
Issued on 9/30/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/10/2024 ARTIN ZARUKIAN
Corrections Issued 7/11/2024 ARTIN ZARUKIAN
Building Plans Picked Up 7/15/2024 APPLICANT
Plan Check Approved 9/27/2024 GURUNATH NESARAJAH
Issued 9/30/2024 APPLICANT
CofO in Progress 9/16/2025 JOHN KIDWELL
Permit Finaled 9/30/2025 JOHN JANSON
CofO Issued 9/30/2025 JOHN JANSON
Permit Finaled 9/30/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/26/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 7/26/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 7/29/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/27/2025 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 3/4/2025 Approved JOHN KIDWELL
Deputy Drilled-In Anchors 3/18/2025 Partial Approval JOHN KIDWELL
Deputy Steel/Welding 4/1/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval JOHN KIDWELL
HVAC-Rough 5/14/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 5/14/2025 Approved JOHN KIDWELL
Rough-Elec/Plmb/HVAC 5/14/2025 Partial Approval JOHN KIDWELL
Sewer 5/14/2025 Approved JOHN KIDWELL
ELECTRICAL-Rough 5/16/2025 Approved JOHN KIDWELL
PLUMBING-Rough 5/16/2025 Approved JOHN KIDWELL
Insulation 5/23/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/28/2025 Approved JOHN KIDWELL
Green Building Rough 5/28/2025 Approved JOHN KIDWELL
Wood Frame 5/28/2025 Approved JOHN KIDWELL
Drywall Nailing 6/3/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/12/2025 Partial Approval JOHN KIDWELL
Shower Pan 6/12/2025 Approved JOHN KIDWELL
Gas Test 7/25/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 8/11/2025 Not Ready for Inspection JOHN KIDWELL
Final 8/11/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 8/11/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 8/11/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 8/11/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 8/11/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 8/27/2025 Approved JOHN KIDWELL
Final 8/27/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 8/27/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 8/27/2025 Approved JOHN KIDWELL
PLUMBING-Final 8/27/2025 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Approved JOHN KIDWELL
ELECTRICAL-Final 9/10/2025 Approved JOHN KIDWELL
Final 9/10/2025 OK to Issue CofO JOHN KIDWELL
Green Building Final 9/10/2025 Approved JOHN KIDWELL
HVAC-Final 9/10/2025 Approved JOHN KIDWELL
PLUMBING-Final 9/10/2025 Approved JOHN KIDWELL
Final 9/16/2025 Not Ready for Inspection JOHN KIDWELL