7359-7361 N OSTROM AVE 91406
Certificate Information: 7359-7361 N OSTROM AVE 91406
- Application / Permit
- 24014-20000-02877
- Plan Check / Job No.
- B24VN09276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2nd floor addition to (E) SFD for a new ADU per ordinance. Demo (E) carport and replace it with a new garage and carport. Fire sprinkler req'd
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- CofO in Progress on 6/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | WEIJIAN HUANG |
| Corrections Issued | 7/15/2024 | WEIJIAN HUANG |
| Quality Review Completed | 7/25/2024 | DANIEL CHAN |
| Applicant returned to address corrections | 10/24/2024 | WEIJIAN HUANG |
| Plan Check Approved | 11/7/2024 | WEIJIAN HUANG |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 6/12/2026 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| Hold | Cleared | 7/15/2024 | ALEXIS SCHULTZ |
| Address approval | Cleared | 8/1/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/1/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 9/6/2024 | RYAN CASTRO |
| Miscellaneous | Cleared | 10/31/2024 | NATHAN ROMINE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sheppard,, Kayse Rose; Lic. No.: NA95444 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/17/2025 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 1/24/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/24/2025 | Approved | GAREN HAYRAPETYAN |
| Sewer | 1/24/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 2/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 2/24/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 2/28/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 4/3/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 5/15/2025 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 5/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 5/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/4/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 6/4/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 6/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 6/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Wood Frame | 6/25/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/2/2025 | Conditional Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 7/2/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/2/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 7/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 8/5/2025 | Approved | JOSE AVILA |
| Green Building Rough | 8/5/2025 | Approved | JOSE AVILA |
| Insulation | 8/11/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 8/27/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 11/26/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 12/9/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Final | 5/26/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | JENNIFER RABUCHIN |