16641-16643 W ADDISON ST 91436
Certificate Information: 16641-16643 W ADDISON ST 91436
- Application / Permit
- 24014-20000-02861
- Plan Check / Job No.
- B24VN09224
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 1713 SF SFD W/ 2' OF WALL AND FOUNDATION TO REMAIN AT WESTERN PORTION. REBUILD 56' X 80'-6" IRREGULAR SHAPED 2-STORY SFD W/ ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- CofO Issued on 9/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | RAPHAEL ROSAS |
| Corrections Issued | 7/8/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 7/10/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/11/2024 | APPLICANT |
| Applicant returned to address corrections | 8/27/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 9/3/2024 | RAPHAEL ROSAS |
| Issued | 9/4/2024 | APPLICANT |
| CofO in Progress | 8/2/2025 | SEAN WIRCH |
| CofO in Progress | 9/3/2025 | SEAN WIRCH |
| Permit Finaled | 9/8/2025 | JOHN JANSON |
| CofO Issued | 9/8/2025 | JOHN JANSON |
| Permit Finaled | 9/8/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 7/22/2024 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 7/24/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/25/2024 | TAL SHEMEN |
| Trees in Parkway | Cleared | 8/23/2024 | MIGUEL ORNELAS |
| Permit | Cleared | 8/26/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/19/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/25/2024 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/30/2024 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/4/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 1/17/2025 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 1/22/2025 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 1/29/2025 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/29/2025 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 1/29/2025 | Partial Approval | THOMAS FINNILA |
| MERV13>=Rough | 1/29/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/31/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 1/31/2025 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/4/2025 | Partial Approval | JON MCHUGH |
| Wood Frame | 2/4/2025 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 2/7/2025 | Approved | THOMAS FINNILA |
| Wood Frame | 2/7/2025 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/12/2025 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 2/13/2025 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 2/13/2025 | Approved | THOMAS FINNILA |
| Insulation | 2/13/2025 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 2/19/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 2/26/2025 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 3/13/2025 | Partial Approval | MORRIS JACKSON |
| Deputy Wood Construction | 3/14/2025 | Conditional Approval | MORRIS JACKSON |
| Drywall Nailing | 3/14/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 7/31/2025 | Approved | SEAN WIRCH |
| Final | 7/31/2025 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 7/31/2025 | Approved | SEAN WIRCH |
| HVAC-Final | 7/31/2025 | Approved | SEAN WIRCH |
| MERV13>=Final | 7/31/2025 | Approved | SEAN WIRCH |
| PLUMBING-Final | 7/31/2025 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 7/31/2025 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 7/31/2025 | Approved | SEAN WIRCH |
| Service/Power Release | 8/25/2025 | Approved | SEAN WIRCH |