3627 S GREENFIELD AVE 90034
Certificate Information: 3627 S GREENFIELD AVE 90034
- Application / Permit
- 24014-20000-02860
- Plan Check / Job No.
- B24VN09215
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST AND 2ND FLOOR ADDITION (1137 SQFT) OF AN ADU TO AN EXISTING DETACHED 2-CAR GARAGE PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | PETER MOSESIAN |
| Corrections Issued | 7/23/2024 | PETER MOSESIAN |
| Quality Review Completed | 7/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/31/2024 | APPLICANT |
| Plan Check Approved | 2/26/2025 | DANIEL ABRAMYAN |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | ARAM AVEDISIAN |
| Permit Finaled | 2/2/2026 | RICHARD STEINBACH |
| CofO Issued | 2/2/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/2/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | DINAH GARIN |
| Sewer availability | Cleared | 8/6/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 8/10/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 8/15/2024 | JOSHUA JONES |
| Construction near power lines | Cleared | 8/16/2024 | RIDWAN HARDY |
Contact Information
| Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | 20520 OXNARD ST WOODLAND, CA 91367 |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2025 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/30/2025 | Conditional Approval | WILBER ROSALES |
| Footing/Foundation/Slab | 5/1/2025 | Approved | ARAM AVEDISIAN |
| Sewer | 5/1/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Approved | WILBER ROSALES |
| HVAC-Rough | 7/18/2025 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 7/18/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 8/29/2025 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 8/29/2025 | Approved | KIRK SANDERS |
| Green Building Rough | 8/29/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 8/29/2025 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 8/29/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/3/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Insulation | 9/3/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Drywall Nailing | 9/9/2025 | Partial Approval | KIRK SANDERS |
| Final | 9/9/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 9/9/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 9/12/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/24/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 12/24/2025 | Corrections Issued | KIRK SANDERS |
| Final | 12/24/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 12/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 12/24/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 12/24/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 12/24/2025 | Approved | KIRK SANDERS |
| Final | 1/16/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 1/16/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 1/30/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 1/30/2026 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 1/30/2026 | Approved | ARAM AVEDISIAN |