3627 S GREENFIELD AVE 90034

Certificate Information: 3627 S GREENFIELD AVE 90034

Application / Permit
24014-20000-02860
Plan Check / Job No.
B24VN09215
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST AND 2ND FLOOR ADDITION (1137 SQFT) OF AN ADU TO AN EXISTING DETACHED 2-CAR GARAGE PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 2/26/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 PETER MOSESIAN
Corrections Issued 7/23/2024 PETER MOSESIAN
Quality Review Completed 7/29/2024 OMID HEDAYAT
Building Plans Picked Up 7/31/2024 APPLICANT
Plan Check Approved 2/26/2025 DANIEL ABRAMYAN
Issued 2/26/2025 APPLICANT
CofO in Progress 1/30/2026 ARAM AVEDISIAN
Permit Finaled 2/2/2026 RICHARD STEINBACH
CofO Issued 2/2/2026 RICHARD STEINBACH
Permit Finaled 2/2/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/6/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/6/2024 DINAH GARIN
Sewer availability Cleared 8/6/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 8/10/2024 LIAM ODONOVAN
Specific Plan Cleared 8/15/2024 JOSHUA JONES
Construction near power lines Cleared 8/16/2024 RIDWAN HARDY

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/25/2025 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 4/30/2025 Conditional Approval WILBER ROSALES
Footing/Foundation/Slab 5/1/2025 Approved ARAM AVEDISIAN
Sewer 5/1/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Approved WILBER ROSALES
HVAC-Rough 7/18/2025 Approved WILBER ROSALES
PLUMBING-Rough 7/18/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 8/29/2025 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 8/29/2025 Approved KIRK SANDERS
Green Building Rough 8/29/2025 Approved KIRK SANDERS
HVAC-Final 8/29/2025 Corrections Issued KIRK SANDERS
Shower Pan 8/29/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/3/2025 Not Ready for Inspection JAYLIN GRAVITTE
Insulation 9/3/2025 Corrections Issued JAYLIN GRAVITTE
Drywall Nailing 9/9/2025 Partial Approval KIRK SANDERS
Final 9/9/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 9/9/2025 Approved KIRK SANDERS
Drywall Nailing 9/12/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 12/24/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/24/2025 Corrections Issued KIRK SANDERS
Final 12/24/2025 Corrections Issued KIRK SANDERS
Green Building Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 12/24/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 12/24/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 12/24/2025 Approved KIRK SANDERS
Final 1/16/2026 Corrections Issued KIRK SANDERS
Green Building Final 1/16/2026 Not Ready for Inspection KIRK SANDERS
Final 1/30/2026 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 1/30/2026 Approved ARAM AVEDISIAN
Service/Power Release 1/30/2026 Approved ARAM AVEDISIAN