11950 N SALEM DR 91344
Certificate Information: 11950 N SALEM DR 91344
- Application / Permit
- 24014-20000-02830
- Plan Check / Job No.
- B24VN09133
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (N) BEDROOM, TWO BATHROOMS & EXPAND (E) LIVING ROOM (47'-8" X 16'), RELOCATE (E) MASTER BEDROOM, ADD (N) PATIO COVER (36'-9" X 10'); INTERIOR REMODEL **ePlan**
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- CofO in Progress on 6/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/6/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/14/2024 | JASON HEALEY |
| Applicant returned to address corrections | 11/5/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/14/2024 | NILOOFAR MEHRAIN |
| Issued | 12/4/2024 | APPLICANT |
| CofO in Progress | 6/2/2026 | STEVEN BACK |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/6/2024 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 8/6/2024 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 9/18/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 9/19/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2025 | Corrections Issued | STEVEN BACK |
| Deputy Drilled-In Anchors | 5/14/2025 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 5/15/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/2/2025 | Approved | STEVEN BACK |
| Wood Frame | 6/2/2025 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | STEVEN BACK |
| Insulation | 6/6/2025 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 6/30/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 7/18/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 7/18/2025 | Approved | STEVEN BACK |
| Deputy Wood Construction | 7/22/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Approved | STEVEN BACK |
| Shower Pan | 7/31/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 8/1/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 8/1/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | STEVEN BACK |
| Green Building Rough | 8/19/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/19/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 8/29/2025 | Approved | STEVEN BACK |
| Insulation | 8/29/2025 | Approved | STEVEN BACK |
| Special/Order Compliance | 8/29/2025 | Corrections Issued | STEVEN BACK |
| Final | 3/2/2026 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/2/2026 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/2/2026 | Approved | STEVEN BACK |
| Final | 4/10/2026 | Corrections Issued | STEVEN BACK |
| Final | 6/2/2026 | OK to Issue CofO | STEVEN BACK |