8951 N FARRALONE AVE 91304
Certificate Information: 8951 N FARRALONE AVE 91304
- Application / Permit
- 24014-20000-02800
- Plan Check / Job No.
- B24VN09058
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: IRREGULAR SHAPED ADDITIONS TO (E) S.F.D. TO INCREASE BEDROOM SIZE AND CREATE A BATHROOM WITH (N) ATTACHED PATIO COVER AND INTERIOR REMODEL PER ENGINEER
- Permit Issued
- Issued on 5/12/2025
- Issuing Office
- Current Status
- Issued on 5/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | ALFRED RAMIREZ |
| Corrections Issued | 7/26/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 8/2/2024 | STEVEN KIM |
| Applicant returned to address corrections | 10/30/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 4/14/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 5/12/2025 | ALFRED RAMIREZ |
| Issued | 5/12/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/29/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 7/29/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2024 | CARLOS RAMIREZ |
| ZA Case | Cleared | 1/15/2025 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 4/14/2025 | ALFRED RAMIREZ |
Contact Information
| Contractor | All Stars Builders Inc; Lic. No.: 1090757-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/10/2025 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/10/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 12/12/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 12/18/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/19/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 12/30/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/30/2025 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2026 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/26/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 1/26/2026 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/26/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 1/26/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/26/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/26/2026 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/29/2026 | Approved | TROY SANDERS |
| Green Building Rough | 1/29/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/29/2026 | Partial Inspection | TROY SANDERS |
| Insulation | 2/3/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/3/2026 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/5/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 3/10/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/10/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/10/2026 | Approved | CHRIS CHRISTENSEN |