19948 W SATICOY ST 91306

Certificate Information: 19948 W SATICOY ST 91306

Application / Permit
24014-20000-02794
Plan Check / Job No.
B24VN09038
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN:REMODEL AND ADDITION OF 6'-5" x 22'-0" (NORTH) AND IRREGULAR SHAPED 2-STORY 23'-8 1/2" x 45'-11" (SOUTH) TO (E) S.F.D. WITH BALCONIES PER ENGINEERING
Permit Issued
Issued on 9/24/2024
Issuing Office
Current Status
CofO Issued on 4/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 ALFRED RAMIREZ
Corrections Issued 7/17/2024 ALFRED RAMIREZ
Quality Review Completed 7/19/2024 STEVEN KIM
Applicant returned to address corrections 8/21/2024 ALFRED RAMIREZ
Plan Check Approved 9/16/2024 ALFRED RAMIREZ
Issued 9/24/2024 APPLICANT
CofO in Progress 2/9/2026 ALEXANDER HANDY
Permit Finaled 4/18/2026 MICHAEL PELHAM
CofO Issued 4/18/2026 MICHAEL PELHAM
Permit Finaled 4/18/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/14/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/14/2024 RYAN CASTRO
Sewer availability Cleared 8/14/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/17/2024 Conditional Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 10/18/2024 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 10/25/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/4/2024 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 11/4/2024 Partial Approval ALEXANDER HANDY
Deputy Wood Construction 11/18/2024 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 11/20/2024 Partial Approval ALEXANDER HANDY
Green Building Rough 11/20/2024 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 12/30/2024 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 12/30/2024 Approved ALEXANDER HANDY
HVAC-Rough 1/17/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/17/2025 Partial Approval KRISTEN CAUSEY
Shower Pan 1/17/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 1/21/2025 Corrections Issued SCOTT SOBEL
BUILDING-Rough-Frame 1/24/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 1/24/2025 Approved JUAN ALVARADO
Green Building Rough 1/24/2025 Approved JUAN ALVARADO
Special/Order Compliance 1/24/2025 Partial Inspection SEAN WIRCH
Insulation 1/31/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/7/2025 Approved JUAN ALVARADO
Drywall Nailing 2/12/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 8/7/2025 Approved SEAN WIRCH
Final 8/7/2025 Corrections Issued SEAN WIRCH
HVAC-Final 8/7/2025 Approved SEAN WIRCH
PLUMBING-Final 8/7/2025 Approved SEAN WIRCH
Final 2/6/2026 OK to Issue CofO ALEXANDER HANDY
Green Building Final 2/6/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 2/6/2026 Approved ALEXANDER HANDY