8024 S EL MANOR AVE 90045
Certificate Information: 8024 S EL MANOR AVE 90045
- Application / Permit
- 24014-20000-02789
- Plan Check / Job No.
- B24VN08994
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL; REMOVE DWELLING EXCEPT FOR 16'-3" PORTION OF WALL ON WEST SIDE OF WALL; ADD 62'-6" X 49'-5" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | SELLA BENYAMIN |
| Corrections Issued | 7/2/2024 | SELLA BENYAMIN |
| Quality Review Completed | 7/2/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/8/2024 | APPLICANT |
| Plan Check Approved | 9/24/2024 | SELLA BENYAMIN |
| Issued | 10/1/2024 | APPLICANT |
| CofO in Progress | 7/23/2025 | RUBEN RIVAS |
| Permit Finaled | 8/21/2025 | RICHARD STEINBACH |
| CofO Issued | 8/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 7/16/2024 | DINAH GARIN |
| Sewer availability | Cleared | 7/16/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/30/2024 | DINAH GARIN |
| Trees in Parkway | Cleared | 9/11/2024 | ADALBERTO VERA |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/13/2024 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 11/13/2024 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 11/20/2024 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 12/3/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 12/3/2024 | Approved | MICHAEL ALLEN |
| Wood Frame | 12/3/2024 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | MICHAEL ALLEN |
| HVAC-Rough | 2/11/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 2/12/2025 | Corrections Issued | MICHAEL ALLEN |
| Deputy Wood Construction | 2/14/2025 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/14/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/19/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 2/19/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | JAYLIN GRAVITTE |
| Shower Pan | 2/27/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/3/2025 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 3/3/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Rough | 3/6/2025 | Approved | MICHAEL ALLEN |
| Insulation | 3/6/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 3/6/2025 | Partial Approval | RUBEN RIVAS |
| Drywall Nailing | 3/13/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/13/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/13/2025 | Partial Inspection | BOBBY KEY |
| Sewer | 4/2/2025 | Approved | RUBEN RIVAS |
| Insulation | 6/26/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Underground Mechanical | 6/26/2025 | Approved | JAYLIN GRAVITTE |
| HVAC-Final | 7/14/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 7/15/2025 | Partial Approval | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 7/16/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 7/17/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 7/17/2025 | Approved | RUBEN RIVAS |
| Service/Power Release | 7/17/2025 | Approved | RUBEN RIVAS |
| Final | 7/23/2025 | OK to Issue CofO | RUBEN RIVAS |
| Green Building Final | 7/23/2025 | Approved | RUBEN RIVAS |
| METHANE-Final | 7/23/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 7/23/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 7/23/2025 | Approved | RUBEN RIVAS |