7718 N MAESTRO AVE 91304
Certificate Information: 7718 N MAESTRO AVE 91304
- Application / Permit
- 24014-20000-02787
- Plan Check / Job No.
- B24VN08985
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 19'-3" X 8'-5" FIRT FLOOR; ADD 33'-10 X 8' SECOND FLOOR TO EXISTING SINGLE FAMILY DWELLING; ADD NEW 33'-10" X 13'-2" PATIO TO THE REAR OF DWELLING; INTERIOR REMODEL
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | SELLA BENYAMIN |
| Corrections Issued | 7/2/2024 | SELLA BENYAMIN |
| Quality Review Completed | 7/3/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/3/2024 | APPLICANT |
| Plan Check Approved | 8/6/2024 | SELLA BENYAMIN |
| Issued | 8/6/2024 | APPLICANT |
| CofO in Progress | 4/8/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/30/2025 | JOHN JANSON |
| CofO Issued | 4/30/2025 | JOHN JANSON |
| Permit Finaled | 4/30/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/2/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 7/9/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/7/2024 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 8/12/2024 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/16/2024 | Partial Approval | JEFFREY HARTLINE |
| Green Building Rough | 9/16/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 9/26/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/26/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/3/2024 | Approved | JEFFREY HARTLINE |
| Shower Pan | 10/3/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/8/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 10/8/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/24/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/24/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 10/24/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 10/24/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/24/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/28/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/28/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 11/7/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 11/12/2024 | Approved | JEFFREY HARTLINE |
| Gas Test | 2/12/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 3/24/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 3/24/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/24/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 3/24/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/24/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/24/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 4/7/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 4/7/2025 | Approved | CHRIS CHRISTENSEN |