9039 N WOODLEY AVE 91343
Certificate Information: 9039 N WOODLEY AVE 91343
- Application / Permit
- 24014-20000-02777
- Plan Check / Job No.
- B24VN08951
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert existing detached garage to ADU with addition per ordinance , all work per Engineer Design.
- Permit Issued
- Issued on 8/4/2024
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | MINA HABILI |
| Corrections Issued | 6/29/2024 | MINA HABILI |
| Applicant returned to address corrections | 7/19/2024 | ZAW HAN |
| Plan Check Approved | 7/24/2024 | ZAW HAN |
| Issued | 8/4/2024 | APPLICANT |
| CofO in Progress | 3/4/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
| CofO Issued | 3/25/2025 | RUBEN SALAS |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/8/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nguyen,, Chuc Ich; Lic. No.: C38556 | 11 VINCENNES NEWPORT COAST, CA 92657 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/6/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/11/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/16/2024 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 9/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/24/2024 | Approved | RAUL OLAGI |
| Sewer | 9/24/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 9/24/2024 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/16/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/16/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/16/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/23/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/23/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/23/2024 | Approved | GAREN HAYRAPETYAN |
| Gas Test | 11/13/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/13/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/2/2024 | Approved | GAREN HAYRAPETYAN |
| Insulation | 12/9/2024 | Corrections Issued | MICHAEL CORTEZ |
| Insulation | 12/16/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 12/24/2024 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 1/15/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 2/8/2025 | Corrections Issued | RAUL OLAGI |
| Final | 2/8/2025 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 2/8/2025 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 2/8/2025 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/21/2025 | Partial Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 2/21/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 2/21/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 2/21/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 2/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | SALVADOR MARTINEZ |
| Final | 2/28/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 2/28/2025 | Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 2/28/2025 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 2/28/2025 | Conditional Approval | RAUL OLAGI |