8416 N LEHIGH AVE 91352
Certificate Information: 8416 N LEHIGH AVE 91352
- Application / Permit
- 24014-20000-02772
- Plan Check / Job No.
- B24VN08936
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO (E) SFD. REMOVE (E) 1-CAR CARPORT. IRR SHAPED ADDN TO EXPAND LIVING RM, DINING RM & KITCHEN, AND FOR NEW HALLWAY, NEW BEDROOM W/ CLOSET & BATHRM PER PLAN. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 6/29/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 7/3/2024 | APPLICANT |
| Plan Check Approved | 8/20/2024 | ANGELICA MARTINEZ |
| Issued | 8/21/2024 | APPLICANT |
| CofO in Progress | 4/26/2026 | DAVID ANDERSON |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
| CofO Issued | 5/11/2026 | RUBEN SALAS |
| Permit Finaled | 5/11/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/6/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/8/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2024 | Corrections Issued | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 9/9/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/9/2024 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/26/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Partial Approval | DAVID ANDERSON |
| Insulation | 10/2/2024 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/4/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 11/4/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 11/4/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Special/Order Compliance | 11/4/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/15/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/15/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 11/15/2024 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 11/15/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/15/2024 | Approved | DAVID ANDERSON |
| Insulation | 11/21/2024 | Partial Approval | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/21/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/2/2024 | Approved | DAVID ANDERSON |
| Final | 5/19/2025 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 5/19/2025 | Approved | DAVID MATSON |
| Green Building Final | 5/19/2025 | Approved | DAVID MATSON |
| MERV13>=Final | 5/19/2025 | Partial Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 5/19/2025 | Approved | DAVID MATSON |
| Final | 11/12/2025 | Corrections Issued | DAVID ANDERSON |
| MERV13>=Final | 11/12/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | DAVID ANDERSON |
| Final | 3/6/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/3/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/10/2026 | OK to Issue CofO | DAVID ANDERSON |