2744 S WESTGATE AVE 90064

Certificate Information: 2744 S WESTGATE AVE 90064

Application / Permit
24014-20000-02769
Plan Check / Job No.
B24VN08931
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert and addition to 14' x 24' detached one story rec room to new two story 15' 8" x 31' 3" ADU per LAMC 12.22 A.33(c)* and (d)*. All work done per engineer.
Permit Issued
Issued on 9/3/2024
Issuing Office
San Pedro
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 NAREG ATARIAN
Corrections Issued 7/13/2024 NAREG ATARIAN
Quality Review Completed 7/15/2024 OMID HEDAYAT
Building Plans Picked Up 7/16/2024 APPLICANT
Plan Check Approved 8/30/2024 NAREG ATARIAN
Issued 9/3/2024 APPLICANT
CofO in Progress 11/7/2025 KIRK SANDERS
Permit Finaled 11/10/2025 RICHARD STEINBACH
CofO Issued 11/10/2025 RICHARD STEINBACH
Permit Finaled 11/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/31/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 8/5/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/6/2024 DINAH GARIN
Sewer availability Cleared 8/6/2024 DINAH GARIN
Specific Plan Cleared 8/6/2024 FREDDY GARCIA
Construction near power lines Cleared 8/21/2024 RIDWAN HARDY
Construction within easement Cleared 8/21/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2025 Corrections Issued WILBER ROSALES
PLUMBING-Rough 4/9/2025 Partial Approval WILBER ROSALES
Deputy Drilled-In Anchors 4/14/2025 Conditional Approval WILBER ROSALES
Footing/Foundation/Slab 4/14/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued WILBER ROSALES
Final 6/13/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 6/13/2025 Partial Approval KIRK SANDERS
Rough-Elec/Plmb/HVAC 6/13/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/17/2025 Approved WILBER ROSALES
Green Building Rough 6/17/2025 Approved WILBER ROSALES
Insulation 6/25/2025 Corrections Issued WILBER ROSALES
Insulation 6/26/2025 Not Ready for Inspection WILBER ROSALES
Shower Pan 6/26/2025 Approved WILBER ROSALES
Drywall Nailing 6/30/2025 Approved WILBER ROSALES
Insulation 6/30/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 6/30/2025 Approved WILBER ROSALES
Gas Test 9/12/2025 Approved KIRK SANDERS
Underground Mechanical 9/12/2025 Approved KIRK SANDERS
ELECTRICAL-Final 9/30/2025 Corrections Issued KIRK SANDERS
Final 9/30/2025 Corrections Issued KIRK SANDERS
Green Building Final 9/30/2025 Approved KIRK SANDERS
HVAC-Final 9/30/2025 Approved KIRK SANDERS
PLUMBING-Final 9/30/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/30/2025 Corrections Issued KIRK SANDERS
Final 11/6/2025 OK to Issue CofO KIRK SANDERS
Service/Power Release 11/6/2025 Approved KIRK SANDERS
Smoke Detectors 11/6/2025 Approved KIRK SANDERS