2744 S WESTGATE AVE 90064
Certificate Information: 2744 S WESTGATE AVE 90064
- Application / Permit
- 24014-20000-02769
- Plan Check / Job No.
- B24VN08931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert and addition to 14' x 24' detached one story rec room to new two story 15' 8" x 31' 3" ADU per LAMC 12.22 A.33(c)* and (d)*. All work done per engineer.
- Permit Issued
- Issued on 9/3/2024
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 11/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | NAREG ATARIAN |
| Corrections Issued | 7/13/2024 | NAREG ATARIAN |
| Quality Review Completed | 7/15/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2024 | APPLICANT |
| Plan Check Approved | 8/30/2024 | NAREG ATARIAN |
| Issued | 9/3/2024 | APPLICANT |
| CofO in Progress | 11/7/2025 | KIRK SANDERS |
| Permit Finaled | 11/10/2025 | RICHARD STEINBACH |
| CofO Issued | 11/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | DINAH GARIN |
| Sewer availability | Cleared | 8/6/2024 | DINAH GARIN |
| Specific Plan | Cleared | 8/6/2024 | FREDDY GARCIA |
| Construction near power lines | Cleared | 8/21/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | WILBER ROSALES |
| Deputy Drilled-In Anchors | 4/14/2025 | Conditional Approval | WILBER ROSALES |
| Footing/Foundation/Slab | 4/14/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Corrections Issued | WILBER ROSALES |
| Final | 6/13/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 6/13/2025 | Partial Approval | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 6/13/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/17/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 6/17/2025 | Approved | WILBER ROSALES |
| Insulation | 6/25/2025 | Corrections Issued | WILBER ROSALES |
| Insulation | 6/26/2025 | Not Ready for Inspection | WILBER ROSALES |
| Shower Pan | 6/26/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 6/30/2025 | Approved | WILBER ROSALES |
| Insulation | 6/30/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 6/30/2025 | Approved | WILBER ROSALES |
| Gas Test | 9/12/2025 | Approved | KIRK SANDERS |
| Underground Mechanical | 9/12/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/30/2025 | Corrections Issued | KIRK SANDERS |
| Final | 9/30/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/30/2025 | Approved | KIRK SANDERS |
| HVAC-Final | 9/30/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 9/30/2025 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 9/30/2025 | Corrections Issued | KIRK SANDERS |
| Final | 11/6/2025 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 11/6/2025 | Approved | KIRK SANDERS |
| Smoke Detectors | 11/6/2025 | Approved | KIRK SANDERS |