3617 S HILLCREST DR 90016

Certificate Information: 3617 S HILLCREST DR 90016

Application / Permit
24014-20000-02768
Plan Check / Job No.
B24VN08929
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO ENLARGE KITCHEN, LIVING ROOM, BEDROOM, AND ADD ONE NEW BATHROOM. NEW PATIO COVER ADDITION TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/18/2024
Issuing Office
Current Status
CofO Issued on 12/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2024 APPLICANT
Assigned to Plan Check Engineer 7/1/2024 JEROME MAGAT PALMA
Corrections Issued 7/2/2024 JEROME MAGAT PALMA
Building Plans Picked Up 7/8/2024 APPLICANT
Applicant returned to address corrections 7/30/2024 GIOVANNY CHAVEZ
Plan Check Approved 9/13/2024 ISIS ARGUETA
Plan Check Approved 9/13/2024 ISIS ARGUETA
Issued 9/18/2024 APPLICANT
CofO in Progress 12/9/2025 WILLIAM MICHALAK
Permit Finaled 12/9/2025 CLAUDIO MORENO
CofO Issued 12/9/2025 CLAUDIO MORENO
Permit Finaled 12/9/2025 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/8/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 7/8/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/3/2024 No Access for Inspection WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 10/7/2024 Corrections Issued WILLIAM MICHALAK
Wood Frame 10/17/2024 Corrections Issued WILLIAM MICHALAK
Insulation 10/21/2024 Approved LUIS CORRAL
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 12/9/2024 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 2/12/2025 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 2/12/2025 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 2/12/2025 Not Ready for Inspection WILLIAM MICHALAK
HVAC-Rough 2/12/2025 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 2/12/2025 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 2/21/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 2/21/2025 Corrections Issued WILLIAM MICHALAK
Insulation 3/24/2025 Corrections Issued WILLIAM MICHALAK
Interior/Exterior Lathing 3/24/2025 Not Ready for Inspection WILLIAM MICHALAK
Shower Pan 3/24/2025 Not Ready for Inspection WILLIAM MICHALAK
Interior/Exterior Lathing 3/27/2025 Approved LUIS CORRAL
Drywall Nailing 3/28/2025 Partial Approval WILLIAM MICHALAK
Green Building Rough 3/28/2025 Partial Approval WILLIAM MICHALAK
Shower Pan 4/1/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 4/3/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 10/22/2025 Corrections Issued WILLIAM MICHALAK
Drywall Nailing 10/22/2025 Partial Approval WILLIAM MICHALAK
ELECTRICAL-Final 10/22/2025 Corrections Issued WILLIAM MICHALAK
Final 10/22/2025 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 10/22/2025 Corrections Issued WILLIAM MICHALAK
Green Building Final 10/22/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 10/22/2025 Corrections Issued WILLIAM MICHALAK
HVAC-Final 10/22/2025 Partial Approval WILLIAM MICHALAK
PLUMBING-Final 10/22/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 10/22/2025 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 10/31/2025 Corrections Issued WILLIAM MICHALAK
Drywall Nailing 10/31/2025 Partial Approval WILLIAM MICHALAK
ELECTRICAL-Final 10/31/2025 Approved WILLIAM MICHALAK
Final 10/31/2025 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 10/31/2025 Corrections Issued WILLIAM MICHALAK
Green Building Final 10/31/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 10/31/2025 Corrections Issued WILLIAM MICHALAK
HVAC-Final 10/31/2025 Corrections Issued WILLIAM MICHALAK
PLUMBING-Final 10/31/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 10/31/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 11/25/2025 Approved WILLIAM MICHALAK
Drywall Nailing 11/25/2025 Approved WILLIAM MICHALAK
Final 11/25/2025 Conditional Approval WILLIAM MICHALAK
Footing/Foundation/Slab 11/25/2025 Approved WILLIAM MICHALAK
Green Building Final 11/25/2025 Approved WILLIAM MICHALAK
Green Building Rough 11/25/2025 Approved WILLIAM MICHALAK
Smoke Detectors 11/25/2025 Approved WILLIAM MICHALAK
Final 12/9/2025 OK to Issue CofO WILLIAM MICHALAK