20313-20315 W VOSE ST 91306

Certificate Information: 20313-20315 W VOSE ST 91306

Application / Permit
24014-20000-02765
Plan Check / Job No.
B24VN08911
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. CONVERT EXISTING ATTACHED GARAGE (388 SF) TO NEW JADU. ADD NEW 60 SQFT COVERED FRONT PORCH FOR SINGLE FAMILY DWELLING. ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 9/12/2024
Issuing Office
Current Status
CofO in Progress on 8/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 NEHEMIAS RAMOS
Corrections Issued 7/12/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 8/23/2024 SUNMIN LEE
Plan Check Approved 9/10/2024 JOSEPH RAFOLS
Issued 9/12/2024 APPLICANT
CofO in Progress 8/4/2026 ALEXANDER HANDY

Permit Application Clearance Information

Address approval Cleared 7/29/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/29/2024 CARLOS AGUILERA
Sewer availability Cleared 7/29/2024 CARLOS AGUILERA
ZI Cleared 8/16/2024 DORIAN AGUILAR
Eng Process Fee Ord 176,300 Cleared 8/21/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/17/2024 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 9/19/2024 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 9/19/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 10/2/2024 Approved ALEXANDER HANDY
ELECTRICAL-Rough 10/9/2024 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 10/11/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 10/25/2024 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 11/4/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/4/2024 Partial Approval KRISTEN CAUSEY
Sewer 11/4/2024 Approved KRISTEN CAUSEY
Insulation 11/7/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 11/7/2024 Partial Approval ALEXANDER HANDY
Drywall Nailing 11/13/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/26/2025 Approved ALEXANDER HANDY
Final 3/26/2025 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 3/26/2025 Approved ALEXANDER HANDY
Green Building Final 3/26/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 3/26/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 3/26/2025 Approved ALEXANDER HANDY
Final 9/16/2025 Not Ready for Inspection ALEXANDER HANDY
Service/Power Release 9/16/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 8/3/2026 Approved ALEXANDER HANDY
Final 8/3/2026 OK to Issue CofO ALEXANDER HANDY
Green Building Final 8/3/2026 Approved ALEXANDER HANDY
HVAC-Final 8/3/2026 Approved ALEXANDER HANDY
PLUMBING-Final 8/3/2026 Approved ALEXANDER HANDY
Service/Power Release 8/3/2026 Approved ALEXANDER HANDY