1138 E 42ND ST 1/4-1/2 90011
Certificate Information: 1138 E 42ND ST 1/4-1/2 90011
- Application / Permit
- 24014-20000-02750
- Plan Check / Job No.
- B24VN08875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) detached garage with addtion to two story two accessroy dwelling units.
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | ARMEN JIVALAGIAN |
| Corrections Issued | 7/2/2024 | ARMEN JIVALAGIAN |
| Quality Review Completed | 7/3/2024 | PETER KIM |
| Applicant returned to address corrections | 1/10/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/31/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/7/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 4/17/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 4/25/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/20/2025 | ARMEN JIVALAGIAN |
| Plan Check Approved | 5/30/2025 | ARMEN JIVALAGIAN |
| Issued | 7/17/2025 | APPLICANT |
| CofO in Progress | 3/11/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/13/2026 | DEROLD HAUFF |
| CofO Issued | 3/13/2026 | DEROLD HAUFF |
| Permit Finaled | 3/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/9/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2024 | WALLIE JONG |
| Sewer availability | Cleared | 7/22/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 8/23/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/23/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/13/2024 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/18/2025 | Conditional Approval | RONNIE MEDINA |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/19/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/20/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 8/20/2025 | Partial Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 8/25/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 10/16/2025 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/20/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 10/20/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 10/22/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 10/22/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 10/22/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 10/22/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 10/24/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/24/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 10/24/2025 | Approved | LUIS CASTRO |
| Insulation | 11/4/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 11/13/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 11/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/9/2026 | Corrections Issued | LUIS CASTRO |
| Gas Test | 1/9/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 1/9/2026 | Approved | LUIS CASTRO |
| Service/Power Release | 2/13/2026 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 2/17/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/17/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/25/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/25/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/26/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/9/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/10/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |