6501 N PONCE AVE 91307

Certificate Information: 6501 N PONCE AVE 91307

Application / Permit
24014-20000-02744
Plan Check / Job No.
B24VN08852
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 14'-10" x 26'-9" ADDITION TO ATTACH (E) SINGLE FAMILY DWELLING TO (E) GARAGE, RE-ROOF AND REMODEL.
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
CofO Issued on 2/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 SARKIS HARABEDIAN
Corrections Issued 6/27/2024 SARKIS HARABEDIAN
Plan Check Approved 7/11/2024 SARKIS HARABEDIAN
Issued 7/30/2024 APPLICANT
CofO in Progress 2/26/2025 GEVORK IPCHYAN
Permit Finaled 2/28/2025 JOHN JANSON
CofO Issued 2/28/2025 JOHN JANSON
Permit Finaled 2/28/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/8/2024 CARLOS AGUILERA
Sewer availability Cleared 7/8/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/9/2024 CARLOS AGUILERA

Contact Information

Contractor New Generation Home Improvements Inc; Lic. No.: 938552-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/20/2024 Conditional Approval TROY SANDERS
PLUMBING-Rough 10/1/2024 Partial Approval GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 10/7/2024 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 10/7/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 11/25/2024 Approved GEVORK IPCHYAN
HVAC-Rough 11/25/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 11/25/2024 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 11/25/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 12/12/2024 Approved GEVORK IPCHYAN
Green Building Rough 12/12/2024 Approved GEVORK IPCHYAN
Insulation 12/12/2024 Approved GEVORK IPCHYAN
Underground Mechanical 12/12/2024 Approved GEVORK IPCHYAN
Drywall Nailing 12/30/2024 Approved TROY SANDERS
Shower Pan 1/7/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 1/14/2025 Partial Approval GEVORK IPCHYAN
Final 2/21/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 2/21/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Final 2/25/2025 Approved GEVORK IPCHYAN
Final 2/25/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 2/25/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 2/25/2025 Approved GEVORK IPCHYAN
Smoke Detectors 2/25/2025 Approved GEVORK IPCHYAN