16116 W HAYNES ST 91406
Certificate Information: 16116 W HAYNES ST 91406
- Application / Permit
- 24014-20000-02716
- Plan Check / Job No.
- B24VN08735
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19'-5" X 25'-6" ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- Issued on 8/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 6/26/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/18/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/24/2024 | DANIEL ABRAMYAN |
| Issued | 8/29/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/29/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2024 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/12/2026 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 3/20/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/27/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/1/2026 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/1/2026 | Partial Approval | KIRK SANDERS |
| PLUMBING-Final | 5/1/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 5/1/2026 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 5/13/2026 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 5/20/2026 | Corrections Issued | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 6/2/2026 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 6/2/2026 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 6/8/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 6/10/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 6/10/2026 | Approved | MICHAEL CORTEZ |
| Shower Pan | 6/10/2026 | Approved | MICHAEL CORTEZ |