13233 W LAKE ST 90066

Certificate Information: 13233 W LAKE ST 90066

Application / Permit
24014-20000-02706
Plan Check / Job No.
B24VN08714
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached 19' 7" x 18' garage to new ADU per CA Govt. Code 65852.2(e)(1)(A), NFPA 13D sprinklers required.
Permit Issued
Issued on 1/7/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 NAREG ATARIAN
Corrections Issued 6/29/2024 NAREG ATARIAN
Quality Review Completed 7/1/2024 OMID HEDAYAT
Building Plans Picked Up 7/2/2024 APPLICANT
Applicant returned to address corrections 9/24/2024 NAREG ATARIAN
Applicant returned to address corrections 10/16/2024 NAREG ATARIAN
Plan Check Approved 10/29/2024 NAREG ATARIAN
Issued 1/7/2025 APPLICANT
CofO in Progress 3/10/2026 ANTHONY EGSON
Permit Finaled 3/25/2026 RICHARD STEINBACH
CofO Issued 3/25/2026 RICHARD STEINBACH
Permit Finaled 3/25/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/5/2024 VASIL MIHALEV
Address approval Cleared 7/10/2024 DARIN LAM
Roof/Waste drainage to street Cleared 7/24/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 7/29/2024 DARIN LAM
Sewer availability Cleared 7/29/2024 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Clayton,, Andrew; Lic. No.: C85452 10211 LEMONA AVE      MISSION HILLS, CA 91345

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2025 Conditional Approval JESUS PINEDA
PLUMBING-Rough 2/28/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 3/10/2025 Approved ARAM AVEDISIAN
Sewer 3/28/2025 Partial Approval MICHAEL ALLEN
Gas Test 4/3/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 4/3/2025 Partial Approval MICHAEL ALLEN
Sewer 4/3/2025 Approved MICHAEL ALLEN
Sewer 5/23/2025 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Approved MICHAEL ALLEN
Gas Test 7/23/2025 Partial Approval WILBER ROSALES
HVAC-Rough 7/23/2025 Approved WILBER ROSALES
PLUMBING-Rough 7/23/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 7/25/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 7/25/2025 Approved WILBER ROSALES
Green Building Rough 7/25/2025 Not Ready for Inspection WILBER ROSALES
Insulation 8/11/2025 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 8/14/2025 Approved JAYLIN GRAVITTE
Green Building Rough 8/14/2025 Approved JAYLIN GRAVITTE
Insulation 8/14/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 8/15/2025 Approved JAYLIN GRAVITTE
Gas Test 11/5/2025 Not Ready for Inspection WILBER ROSALES
Gas Test 11/19/2025 Corrections Issued WILBER ROSALES
Gas Test 12/24/2025 Approved WILBER ROSALES
Service/Power Release 12/24/2025 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Final 1/13/2026 Not Ready for Inspection ANTHONY EGSON
Final 1/13/2026 Corrections Issued ANTHONY EGSON
Green Building Final 1/13/2026 Approved ANTHONY EGSON
HVAC-Final 1/13/2026 Corrections Issued ANTHONY EGSON
PLUMBING-Final 1/13/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved ANTHONY EGSON
Smoke Detectors 1/13/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 1/26/2026 Approved ANTHONY EGSON
Service/Power Release 1/26/2026 Not Ready for Inspection ANTHONY EGSON
Final 2/23/2026 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 2/23/2026 Corrections Issued ANTHONY EGSON
Service/Power Release 2/23/2026 Not Required ANTHONY EGSON
Smoke Detectors 2/23/2026 Approved ANTHONY EGSON
Final 3/9/2026 OK to Issue CofO ANTHONY EGSON
HVAC-Final 3/9/2026 Approved ANTHONY EGSON