13235 W LAKE ST 90066
Certificate Information: 13235 W LAKE ST 90066
- Application / Permit
- 24014-20000-02705
- Plan Check / Job No.
- B24VN08714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and Major Remodel to existing 1 story Single Family Dwelling, only 37' 7 1/2" of exterior wall and foundation to remain on North and West portions of the lot. Rebuilt as 2 story (44' 11" x 44' 10" Irregular Shaped) Single Family Dwelling, with attached Porch, and attached Garage. NFPA 13D fire sprinklers throughout. All work done per engineer.
- Permit Issued
- Issued on 1/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | NAREG ATARIAN |
| Corrections Issued | 6/29/2024 | NAREG ATARIAN |
| Quality Review Completed | 7/1/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 7/2/2024 | APPLICANT |
| Applicant returned to address corrections | 9/24/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/16/2024 | NAREG ATARIAN |
| Plan Check Approved | 10/29/2024 | NAREG ATARIAN |
| Issued | 1/7/2025 | APPLICANT |
| CofO in Progress | 3/10/2026 | ANTHONY EGSON |
| Permit Finaled | 3/25/2026 | RICHARD STEINBACH |
| CofO Issued | 3/25/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/25/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/5/2024 | MATTHEW JENKINS |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | DARIN LAM |
| Permit | Cleared | 7/28/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/29/2024 | DARIN LAM |
| Trees in Parkway | Cleared | 9/25/2024 | DYNL MIRANDA |
| GPI Written Notices | Cleared | 10/16/2024 | MATTHEW JENKINS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Clayton,, Andrew; Lic. No.: C85452 | 10211 LEMONA AVE MISSION HILLS, CA 91345 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2025 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 3/10/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 3/28/2025 | Partial Approval | MICHAEL ALLEN |
| Sewer | 3/28/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | MICHAEL ALLEN |
| Sewer | 5/23/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 5/23/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 7/2/2025 | Conditional Approval | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 7/18/2025 | Partial Approval | MICHAEL ALLEN |
| Gas Test | 7/23/2025 | Partial Approval | WILBER ROSALES |
| HVAC-Rough | 7/23/2025 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 7/23/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 7/25/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 7/25/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 7/25/2025 | Not Ready for Inspection | WILBER ROSALES |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 7/31/2025 | Approved | WILBER ROSALES |
| Insulation | 7/31/2025 | Not Ready for Inspection | WILBER ROSALES |
| Insulation | 8/4/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 8/11/2025 | Approved | WILBER ROSALES |
| Shower Pan | 8/11/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 8/14/2025 | Approved | JAYLIN GRAVITTE |
| Gas Test | 11/5/2025 | Not Ready for Inspection | WILBER ROSALES |
| Gas Test | 11/19/2025 | Corrections Issued | WILBER ROSALES |
| Gas Test | 12/24/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 12/24/2025 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 1/13/2026 | Corrections Issued | ANTHONY EGSON |
| Final | 1/13/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/13/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/13/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 1/13/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/13/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 1/26/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 1/26/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 2/23/2026 | Approved | ANTHONY EGSON |
| Final | 2/23/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 2/23/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 2/23/2026 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 2/23/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 2/23/2026 | Approved | ANTHONY EGSON |
| Final | 3/9/2026 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 3/9/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/9/2026 | Approved | ANTHONY EGSON |